The Noor Ouarzazate III central receiver solar plant with storage completes its reliability test

2018.11.07     From: engineeringandconstruction.sener

The consortium formed by SENER and SEPCO III has completed the reliability test for the 150-MW Noor Ouarzazate III concentrated solar power plant. It is one more step in the start-up of the facility, which is nearing commercial operation and final delivery to the client.


With this reliability test, which ran for ten straight days, Noor Ouarzazate III has demonstrated its ability to output its rated power to the grid under changing weather conditions, and even after sunset, thanks to its molten salt storage system, which can continue to produce electricity in the absence of sunlight for 7.5 hours. Over these 10 days, the plant output over 13.2 GWh to the grid. Once operational, the plant will be able to generate enough electricity to power 120,000 homes, with no atmospheric emissions of CO2.



At Noor Ouarzazate III, SENER is responsible for the conceptual and basic engineering of the plant, the detail engineering and for supplying the equipment for the thermal storage system. It is also responsible for the engineering and the construction of the solar field and the molten salt receiver, and for the comprehensive start-up of the plant. This is the second plant with a central tower and molten-salt storage system designed and built by SENER, which also provided its own technology, the 7,400 HE54 heliostats that constitute the solar field, the solar tracking system, the high-power receiver, with more than 600 MW, and the integrated control system for the receiver and the solar field. This plant is one of the first in the world to apply this configuration on a commercial scale.


Noor Ouarzazate III is part of the Noor solar complex, the largest on the planet, located in Ouarzazate (Morocco) and run by MASEN. In the aforementioned megaproject, SENER is part of the turnkey building consortium for the Noor Ourzazate I and Noor Ouarzazate II plants, both of which feature SENERtrough® cylindrical-parabolic trough technology, and Noor Ourzazate III, with advanced innovations with respect to those applied in Gemasolar, a plant designed and built by SENER which was the first in the world in commercial operartion to rely on a central tower receiver and molten salt storage technology.

Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news