China encourage new CSP technologies in 1st batch demos

2018.11.29     From: CSP Focus光略咨询

  9th Annual CSP Focus China Mar.21-22 Beijing  



Among China 1st batch of 20 concentrated solar power (CSP) demonstration projects, there are 9 Towers, 7 Troughs and 4 CLFRs, all of which were designed with huge capacity multi-hour storage system.

One of the inherent targets of the implementation of CSP pilot projects is to encourage the application of new CSP technologies.

There were many new technologies which will be implemented first time in the world in a commercial project. CSP Focus hereby list 6 kinds of CSP innovations, and 8 typical demos taking these technologies.

Among the 8 pilot CSP projects, 4 are under construction and expected to be completed this year or next year, and 2 are still pending with quite little development, and 2 were claimed cancelation early this year.

Get fully learned of the current situation of China 1st batch of demos, you may free download the 21-page report on China 1st Batch of CSP Pilot Projects Update (Nov-2018 Edition).

1. Silicon oil as the HTF in a trough plant

Royal Tech Yumendongzhen 50MW PT Project:
EPC contract signed with Beijing Shouhang IHW on June 2018;
Construction started on June 2018;

2. Modular Beam Down tower technology

Yumen Xinneng 50MW MS Tower Project:
· Installation of solar field in Module 1 completed; salt melting and solar field commissioning completed;
· Installation of solar field in Module 2/3/5 still in progress and hopefully will be completed by the end of 2018;
· Construction and installation of power block and steam turbine is still in progress, hopefully to be completed early next year;

3. Modified DSG CLFR technology with concrete storage system

Huaqiang Zhaoyang Zhangjiakou DSG 50MW CLFR Project:
Pending with little progress.

CITIC Zhangbei DSG 50MW CLFR Project:
Canceled.

4. Molten salt as the HTF in a trough plant

Shenzhen Jinfan Akesai 50MW molten salt PT Project:
· Foundation of salt tanks completed;
· Solar field assembly workshop completed;

Zhongyang Zhangjiakou Chabei 64MW PT Project:
Pending with little progress.

5. Molten salt as the HTF in a CLFR plant

DCTC Dunhuang 50MW MS CLFR Project:
· Financial closed in June 2018, debt funding from Power China Leasing Co., Ltd; EPC contractor changed to Zhongnan Engineering Co., Ltd of Power China;
· Construction started by the end of 2018;

6. Synthetic oil as the HTF in a CLFR plant

Northern United Power Urad 50MW CLFR Project:
Canceled.

If you would like to get known of the most fresh information and look for customers and partners in China, you are much welcome to join the upcoming 9th Annual CSP Focus China Conference & Exhibition on Mar.21-22 in Beijing, China


Click to get brochure of CSP Focus China 2019 and register before Nov.29, 2018 to SAVE USD 400.

Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news