2018.11.29     From: CSP Focus光略咨询

  9th Annual CSP Focus China Mar.21-22 Beijing  



Among China 1st batch of 20 concentrated solar power (CSP) demonstration projects, there are 9 Towers, 7 Troughs and 4 CLFRs, all of which were designed with huge capacity multi-hour storage system.

One of the inherent targets of the implementation of CSP pilot projects is to encourage the application of new CSP technologies.

There were many new technologies which will be implemented first time in the world in a commercial project. CSP Focus hereby list 6 kinds of CSP innovations, and 8 typical demos taking these technologies.

Among the 8 pilot CSP projects, 4 are under construction and expected to be completed this year or next year, and 2 are still pending with quite little development, and 2 were claimed cancelation early this year.

Get fully learned of the current situation of China 1st batch of demos, you may free download the 21-page report on China 1st Batch of CSP Pilot Projects Update (Nov-2018 Edition).

1. Silicon oil as the HTF in a trough plant

Royal Tech Yumendongzhen 50MW PT Project:
EPC contract signed with Beijing Shouhang IHW on June 2018;
Construction started on June 2018;

2. Modular Beam Down tower technology

Yumen Xinneng 50MW MS Tower Project:
· Installation of solar field in Module 1 completed; salt melting and solar field commissioning completed;
· Installation of solar field in Module 2/3/5 still in progress and hopefully will be completed by the end of 2018;
· Construction and installation of power block and steam turbine is still in progress, hopefully to be completed early next year;

3. Modified DSG CLFR technology with concrete storage system

Huaqiang Zhaoyang Zhangjiakou DSG 50MW CLFR Project:
Pending with little progress.

CITIC Zhangbei DSG 50MW CLFR Project:
Canceled.

4. Molten salt as the HTF in a trough plant

Shenzhen Jinfan Akesai 50MW molten salt PT Project:
· Foundation of salt tanks completed;
· Solar field assembly workshop completed;

Zhongyang Zhangjiakou Chabei 64MW PT Project:
Pending with little progress.

5. Molten salt as the HTF in a CLFR plant

DCTC Dunhuang 50MW MS CLFR Project:
· Financial closed in June 2018, debt funding from Power China Leasing Co., Ltd; EPC contractor changed to Zhongnan Engineering Co., Ltd of Power China;
· Construction started by the end of 2018;

6. Synthetic oil as the HTF in a CLFR plant

Northern United Power Urad 50MW CLFR Project:
Canceled.

If you would like to get known of the most fresh information and look for customers and partners in China, you are much welcome to join the upcoming 9th Annual CSP Focus China Conference & Exhibition on Mar.21-22 in Beijing, China


Click to get brochure of CSP Focus China 2019 and register before Nov.29, 2018 to SAVE USD 400.

Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.