Solar field completed for Power China 50MW molten salt tower CSP project
2019.02.02 From: CSP Focus
Located in
Hainan Eco Solar Energy Park, 12 kilometers southwest to Gonghe County of
Qinghai Province in Northwest China, Power China Gonghe 50MW Molten Salt Tower CSP Project, as one of China first batch of pilot CSP projects, is under great progress and supposed to be commissioned in middle of 2019.
As the project Solar Field EPC SUPCON Solar said to CSP Focus earlier, up to date, all the 30,016 pieces of heliostats have been installed this January, and the concreting of tower receiver was completed at the end of November, 2018.
Thanks to the strong support and commitment from the owner Power China, and the experience and expertise of SUPCON solar, the project is able to be developed and constructed quite smoothly. As a survey launched by CSP Focus earlier to vote on the "2019 Most Anticipated CSP Pilot Project in China", Power China Gonghe project was ranked Number One. Predictably, it would be China fourth or fifth CSP pilot project.
SUPCON Solar was also the owner and developer of China 3rd CSP demonstration CSP project--SUPCON Delingha 50MW molten salt tower CSP project. SUPCON signed the solar field EPC contract with the project EPC Power China Northwest Engineering Corporation Co., Ltd. in February 2018, and started the installation of heliostats on June 28th, 2018. It took around half a year to complete the heliostats, which broke the record made in SUPCON Delingha 50MW tower CSP project.
Milestones of Power China Gonghe 50MW Molten Salt Tower CSP Project:
● January 14th, 2019, heliostats completed
● November 22nd, 2018, Receiver Tower Concreting Completed
● June 28th, 2018, On-site Installation of First Heliostat Completed
● June 18th, 2018, Project Construction Started
● April, 2018, Foundation of Receiver Tower Completed
● November 29th, 2016, Feasibility Study Evaluation and Inspection Meeting held
● September 23rd, 2016, Selected as Pilot Project
● August, 2015, Pre-Feasibility Study Completed
More project details and updates please download the fresh report produced by CSP Focus:
Free Report: Power China Gonghe 50MW Molten Salt Tower CSP Plant (New)
With the total investment of RMB 1.222 billion, and 6 hours' molten salt thermal electricity storage, the project expects an
annual electricity generation of around 156.92GWh after
completion.
Together with SUPCON Solar, Power China SEPCO1 Electric Power Construction Co., Ltd will be responsible of HTF&TES Installation and Commissioning. Overseas companies including Flowserve, MICC, Chromalox provide some of the key products like molten salt pump and valve and heat tracing. More components are manufactured by Chinese local companies, such as mirrors from Daming, steam generator from Shanghai Boiler, steam turbine from Harbin Turbine, molten salt from Qinghai Lianda Chemical Co., Ltd.
To
read the full list of the confirmed vendors for China leading 13 CSP projects
including Power China Gonghe 50MW molten salt Tower CSP Plant, please
click:
Free Report: Suppliers List of China Key CSP Projects (Jan. 2019 Edition)
Upcoming CSP events:
9th Annual CSP Focus China 2019(Mar.21-22, Beijing)
4th Annual CSP Focus MENA 2019(Jun.26-27, Dubai)
More CSP news and reports please visit www.cspfocus.cn
More from CSP Focus
NextChina pilot CSP project--Supcon Solar Delingha 50MW CSP plant
SolarReserve eyes Chile CSP wins as surplus PV disrupts markets
World’s Biggest Solar Thermal Plant To Be Built In Saudi Arabia
ACWA Power, SolarReserve to break ground on 100 MW Concentrated Solar Power plant in South Africa
$2.5 million Department of Energy grant helps MSU engineering professor study solar energy
Concentrated Solar Power plants (CSP) will play a major role in the MENA region
Concentrated Solar Power startup Heliogen scores $39 million in DOE funding
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower