MBR Concentrated Solar Power Park reaches news infrastructure completion phase

2019.04.08     From: helioscsp

The concrete base of the tower that is part of the Mohammed bin Rashid Al Maktoum, MBR, Solar Park, the largest single-site concentrated solar power, CSP, project in the world, has been completed.


Saeed Mohammed Al Tayer, Managing Director and CEO of Dubai Electricity and Water Authority, DEWA, inspected the construction work of the fourth phase of the solar park, based on the independent power producer, IPP, model with a capacity of 950MW costing up to AED15.78 billion.

Once built, the 260-metre structure will be the tallest solar power tower in the world.


Al Tayer was briefed on the progress of construction work by Abdul Hamid Al Muhaidib, Executive Managing Director of Noor Energy 1, a venture formed through a partnership between DEWA, Saudi Arabia’s ACWA Power and China’s Silk Road Fund to build the fourth phase of the park.


Al Muhaidib confirmed the completion of the concrete base that contains about 1,300 tonnes of steel rebar and concrete, equivalent to 20 percent of Paris’s Eiffel Tower. The concrete placed weighs over 19,000 tonnes, equivalent to the weight of 34 full A380s planes’ take-off weight with 555 passengers.


Al Muhaidib explained that 33 percent of the engineering work has been completed for the project, which is proceeding according to plan.


This project is the largest single-site solar IPP project in the world that combines CSP and photovoltaic technology. This phase will provide clean energy for 320,000 residences and will reduce 1.6 million tonnes of carbon emissions annually. The project, which will cover an area of 44 square kilometres, achieved several world records.


These include the world’s lowest CSP Levelised Cost of Electricity, LCoE, of US$7.3 cents per kilowatt-hour and the lowest LCoE for photovoltaic technology of 2.4 US cents per kilowatt-hour. Apart from being the tallest solar tower in the world, it will use 70,000 heliostats, and the largest thermal storage capacity of 15 hours, allowing for energy availability round the clock.


It will generate 5,000MW by 2030 with investments of up to AED50 billion. The 13MW photovoltaic first phase became operational in 2013. The 200MW photovoltaic second phase of the solar park was launched in March 2017 while the 200MW first stage of the 800MW photovoltaic third phase became operational in May 2018. The third phase will be completed in 2020.



Upcoming CSP events:


4th Annual CSP Focus MENA 2019(Jun.26-27, Dubai)

3rd CSP Focus Innovation 2019(Oct.24-25, China)


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook

Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news