Construction progress on MBR Solar Park – Phase 4's 260m solar tower

2019.05.21     From: constructionweekonline

PICTURES: The development of Phase 4's solar tower is 7% ahead of schedule, whilst its solar field is 73% complete


HE Saeed Mohammed Al Tayer, managing director and chief executive officer of Dubai Electricity and Water Authority (Dewa), has received a construction update on Phase 4 of the Mohammed bin Rashid Al Maktoum Solar Park (MBR Solar Park) project, including its 260m-tall solar tower, in Dubai.


Abdul Hamid Al Muhaidib, executive managing director of Noor Energy 1 – the joint venture of Dewa, Saudi Arabia’s Acwa Power, and China’s Silk Road Fund that is tasked with building Phase 4 – briefed Al Tayer during a visit to MBR Solar Park's construction site, as reported by Dubai Media Office (DMO).


Al Muhaidib confirmed that construction work on Phase 4's solar tower was 7% ahead of its planned schedule.


Moreover, 73% of the tower’s solar field also been built, DMO added, including the completion of the main structure for the assembly and installation of heliostats – devices that are used to reflect sunlight in a fixed direction.


Phase 4 of MBR Solar Park is the largest single-site concentrated solar power (CSP) project in the world. Based on the independent power producer (IPP) model, it will generate 950 MW of solar energy following an investment of $4.3m (AED15.78bn).


In total, MBR Solar Park will generate 5,000 MW of electricity by 2030, and is valued at approximately $13.6bn (AED50bn)


The park’s 13 MW Phase 1 began operations in 2013, whilst the 200 MW second phase was launched in March 2017. Phase 3 began operations in May 2018.


In March, American chemical giant Dow announced it had been awarded a subcontract for the Phase 4 along with China’s Shanghai Electric to provide on-ground services related to Dowtherm, a heat transfer fluid capable of resisting temperatures as high as 400°C to collect, transport, and store heat in CSP systems.



Upcoming CSP events:


4th Annual CSP Focus MENA 2019(Jun.26-27, Dubai)

3rd CSP Focus Innovation 2019(Oct.24-25, China)


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.


Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news