Full capacity test a success for concentrated solar power plant in China

2019.06.19     From: CSPFocus光略咨询


The country’s first 100-megawatt molten salt concentrating solar thermal power plant in Dunhuang, Northwest China’s Gansu province, has successfully generated power while operating at full capacity.



Nearly 20 hours of operating records show the systems at the concentrated solar power plant have been normal and stable. The facility also set a new record by generating over 1.8 million kilowatt-hours of power day and night, with all indicators suggesting it has reached or exceeded its designed values.


This marks another important step after the plant created 1.67 million kWh of power over 34 hours of continuous operations in mid-April, the report said.


Unlike wind power or photovoltaic power generation stations, the molten salt can also be stored and used to generate power on demand, even at night, and the system is nonpolluting as well,


Huang Wenbo, vice-chairman of Beijing Shouhang, said the concentrated solar power plant has withstood the test of running under the harshest environmental conditions in different seasons, which means it can be widely used in northwestern areas.



The concentrated solar power plant is among China’s first batch of solar thermal power generation demonstration projects, the report said. With an investment of 3 billion yuan (US$433.1 million), it was built by Beijing Shouhang IHW Resources Saving Technology Co. Ltd., which wholly owns the power station’s intellectual property rights.


The concentrated solar power plant, also called the «super mirror power plant,» works by using 12,000 mirrors that concentrate the sunlight onto a receiver at the top of a solar tower, which then heats the molten salt.


It is designed to generate 390 million kWh of power annually, which can reduce carbon dioxide emissions by 350,000 metric tons per year. That’s equivalent to the annual environmental benefit derived from 667 hectares of forested land.



Upcoming CSP events:


4th Annual CSP Focus MENA 2019(Jun.26-27, Dubai)

3rd CSP Focus Innovation 2019(Oct.24-25, China)


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.


Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news