Detailed Progress on China 1st phase 20 CSP pilot projects

2017.01.24     From: CSP Focus

It has been over 4 months since the official announcement of China 1st phase 20 CSP pilot project list in September 2016. As the government said only those which could be completed by the end of 2018 would enjoy the FiT of RMB1.15/kWh. Thus, around only 23 months are left for construction, which seems to be quite hard work for the project participators. Below are the newly updated progresses of the 20 pilot CSP projects: 

Free report: List of China 1st Phase 20 CSP Pilot Projects


1.Under construction/bidding

1.1 CGN Delingha 50MW Parabolic Trough Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: providers of detailed design, receiver tube, reflector, steam turbine and other key components have been confirmed. Project construction keeps going on even in winter.

1.2 Beijing Shouhang IHW Resources Saving Technology (SunCan) 100MW Molten Salt Tower Project

  • Feasibility study institute: Guangdong Northeast Electric Power Design Institute

  • Recent news: 1st phase of 10MW tower project has been put into operation. 2nd phase of 100MW project is under construction with the tower foundation established. The steam turbine tender has been completed, and some providers of other key components have been confirmed. It is expected to be completed in the mid of 2018.

1.3 Shenzhen Jinfan Akesai 50MW molten salt Parabolic Trough Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: Electricity matching started in 2013, and water diversion project in 2015. Supporting facilities are under construction, and equipment procurement is in the preparation stage.

1.4 Qinghai SUPCON Solar Delingha50MW Molten Salt Tower Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: 1st phase of 10MW tower project has been put into operation. Feasibility study is completed and commencement ceremony has been held. Key components like steam turbine is under procurement.

1.5 Rayspower Group Yumen 50MW Parabolic Trough Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: feasibility study is completed and commencement ceremony has been held. Inner Mongolia Electric Power Survey Design Co., Ltd has been awarded to be responsible for preliminarily design, survey and general design.

1.6 Northwest Electric Power Design Institute Hami 50MW MS Tower Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: feasibility study is completed and commencement ceremony has been held. Biddings for solar field system, steam turbine, SGS, and generator have been launched and the results will come out soon. 

1.7 Zhongyang Chabei 64MW Parabolic Trough Project

  • Feasibility research Institute: Central South Survey Design Institute

  • Recent news: The commencement ceremony was held in 2014. The developer is working on financing. 

1.8 Yumen Xinneng 50MW Molten Salt Tower Project

  • Feasibility study institute: North China Power Engineering Co., Ltd 

  • Recent news: feasibility study is being reviewed and EPC tender is going on.

1.9 Guohua Yumen 100MW Molten Salt Tower Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: feasibility study is completed and EPC tender is going on. The winner will be awarded on Feb.8 out of 6 candidates. 

1.10 China Nuclear Royal Tech Wuzhongqi 100MW Parabolic Trough Project

  • Feasibility study institute: North China Power Engineering Co., Ltd 

  • Recent news: feasibility study is completed and the key component biddings are expected to be open soon. Project construction is expected to start in mid of April.

1.11 Royal Tech Yumendongzhen 50MW Parabolic Trough Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: feasibility review has been finished and key component biddings are expected to be open soon. Project construction is expected to start in mid of April.


2.In preparation stage

2.1 Huanghe Hydropower Development 135MW Molten Salt Tower Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: feasibility study has been finished, and technical route has been changed to molten salt tower.

2.2 Zhangbei Huaqiang Group Zhangjiakou DSG 50MW CLFR Project

  • Feasibility study Institute: Hebei Institute of Survey and Design

  • Recent news: 1st phase of 10MW is expected to operate soon, and feasibility study for the 50 MW project has been completed.

2.3 DCTC Dunhuang 50MW Molten Salt CLFR Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: The feasibility review has been finished.

2.4 Northern United Power Urad 50MW CLFR Project

  • Feasibility study institute: North China Power Engineering Co., Ltd 

  • Recent news: The feasibility study has been finished.

2.5 Dahua Inc. Shangyi 50MW Molten Salt Tower Project

  • Feasibility study institute: Northwest Electric Power Design Institute

  • Recent news: feasibility study review has been started, and technical route has been changed to molten salt tower.

2.6 Northwest Survey&Design Gonghe 50MW Molten Salt Tower Project

  • Feasibility study Institute: Northwest Institute of Survey and Design

  • Recent news: feasibility study review work started in late Nov. and preliminary design is under preparation. 

2.7 CITIC Zhangbei DSG 50MW CLFR Project

  • Feasibility study Institute: Hebei Institute of Survey and Design

  • Recent news: carrying forward

2.8 CECIC Gansu Wuwei 100MW Parabolic Trough Project

  • Feasibility study institute: North China Power Engineering Co., Ltd 

  • Recent news: carrying forward

2.9 China Three Gorges New Energy Jinta 100MW Molten Salt Tower Project

  • Feasibility study institute: North China Power Engineering Co., Ltd 

  • Recent news: carrying forward 

Leave your thoughts here

Free Reports

See more+
  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

  • BrightSource Engineering and Manufacturing System

    Engineering, Supply Chain, Construction, Business Intelligence. What about the Min O&M?

  • Yumen Xinneng 50MW Molten Salt Tower CSP Project

    The project broke ground in June 2017, and 3 of the 15 modules are expected to be connected to the gird by the end of September, 2019. It will be the first large‐scale commercial CSP plant in the world taking innovative beam-down molten salt tower CSP technology.

  • Luneng Haixi 50MW Molten Salt Tower CSP Project

    With total capacity of700MW, Luneng Haixi Geermu Multi-energy Complement Integration OptimizationPilot Project consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energystorage system. Updating--Jan., 2019 Edition1. Overview (P2)2. Highlights (P2)3. Fast sheet (P3)4. Project Milestones (P4)5. Project Participants 5.1. Developer (P5) 5.2. Owner&Investor (P5) 5.3. EPC Contractor (P5)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news