China Luneng Haixi 50MW Tower CSP project to operate end August

2019.07.30     From: CSP Focus光略咨询


Located in Haixi, Qinghai Province in Northwest China, Luneng Haixi 50MW Molten Salt Tower CSP Project is a crucial part of 700MW Luneng Haixi Geermu Multi-energy Complement Integration Optimization Pilot Project, which consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energy storage system.




The 50MW CSP plant, namely Luneng Haixi 50MW Molten Salt Tower CSP Project was started construction on June 30, 2017, and now entering commissioning period before its completion . Mr. ZENG Xuyao, Deputy General Manager of the Project Developer Luneng Qinghai Geermu New Energy Company reported recently on the project progress, saying it is expected to be operational in one month by the end of this August.


At that time, Luneng Haixi project will be the first large-scale commercial solar thermal power plant which is not amongst China 1st batch of CSP demonstration projects, and the 4th CSP plant in China after CGN Delingha 50MW parabolic trough, Shouhang Dunhuang 100MW molten salt tower, and SUPCON Delingha 50MW molten salt tower CSP projects which were connected to the grid last year in 2018.



A total number of 4,400 heliostats (138m² per) will be installed in the solar field covering an area of 610000m². The receiver tower will be 181.1 meters high, of which 147.4 meters are made up of reinforced concrete.


More project details and updates please download the fresh report produced by CSP Focus: 

Free Report: Luneng Haixi 50MW Molten Salt Tower CSP Plant (July 2019 Edition)


Milestones of Luneng Haixi 50MW Molten Salt Tower CSP Project:


 ● 2019-8-30, expected to be operational

 ● 2019-7-4, Steam turbine and generator installed

 ● 2019-4-30, 2,100 heliostats installed (4,400 in total)

 ● 2019-1-2, civil work completed, equipment installation started

 ● 2018-11-21, construction completion of receiver tower (147.4m of 181.1m)

 ● 2018-10, COD of PV and Wind projects

 ● 2017-6-30, project construction started

 ● 2016-12-26, Project approval from National Energy Administration



In terms of the key equipment and service providers, China SEPCOIII Electric Power Construction Co., Ltd., who is also the EPC contractor of Morocco NOORo 2&3 projects, work as the turnkey EPC for the project owner--Luneng Group. European leading CSP firms Abengoa and Fichtner act as the roles of Solar field technology provider and Owner's Engineer respectively.


Other overseas companies including HP Valves, Flowserve, Eltherm, OHL, CMI, MICC, Emerson, BCB, Siemens provide some of the key products like molten salt pump and valve, heat tracing, DCS, steam turbine.


Some components are manufactured by Chinese local companies, such as thermal insulation from Luyang, mirrors from Daming, steam generator from Hangzhou Boiler, hydraulics from Sichuan CRUN.


To read the full list of the confirmed vendors of Luneng Haixi 50MW molten salt Tower CSP Plant, please click: 

Free Report: Luneng Haixi 50MW Molten Salt Tower CSP Plant (July 2019 Edition)



And you are also welcome to join the upcoming 3rd CSP Focus Innovation 2019(Oct.24-25, Beijing China)  conference and expo, where the project developer Luneng and technology provider Abengoa are expected to be present, sharing the fresh updates and experience on Luneng Haixi CSP Project.


Click here to get the event brochure and register BEFORE Aug.1 will SAVE you USD200/per.






Upcoming CSP event:


3rd CSP Focus Innovation 2019(Oct.24-25, Beijing China)

10th CSP Focus China 2020 (March, Beijing China) 


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.


Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news