South African CSP plant records 24-hour output; GE assumes Ashalim EPC role

2016.04.06     From: CSPTODAY

Abengoa's Khi Solar One completes 24-hour commercial output


 

Image credit: erwo1


Abengoa has completed 24 consecutive hours of commercial output at the 50 MW Khi Solar One project in South Africa, the company said March 29. Abengoa previously operated a pilot 5 MW plant where it optimized the storage technology.


By design, the storage system at Khi Solar One can produce 50 MW for two hours after sunset, but because less energy is used at night the company can supply electricity for longer. Abengoa said this is the first tower plant to achieve 24 hours of output with solar energy only.


The Khi Solar One park is owned by Abengoa, Industrial Development Corp (IDC) and the Khi Community Trust. It reached commercial operation on February 2 and, according to Abengoa’s website, it can produce enough electricity to power 45,000 homes each year.


Abengoa and its partners are also working on another CSP project in the country. The 100 MW Xina Solar One project will use parabolic trough technology and will have five hours of storage capacity.


GE takes over EPC duties at Israel's Ashalim project


General Electric (GE) has taken over the engineering, procurement and construction (EPC) duties at BrightSource Energy’s 121 MW Ashalim project, according to press reports.


GE continues to partner with Brightsource and NOY Infrastructure & Energy Investment Fund to build the 121 MW Ashalim Solar Thermal Power Station in Israel’s Negev desert, where Brightsource is deploying new CSP technologies.


GE is now fully responsible for EPC of the solar power station, with BrightSource providing the advanced solar field technology.


The BrightSource-GE-NOY Megalim project is one of three projects selected under Israel’s Ashalim 250 MW solar tender.


More than 50,000 computer-controlled mirrors will track the sun on two axes and reflect sunlight onto a boiler on top of a 250-meter tower.


Construction is underway and the facility is scheduled to be completed in late 2017. When operational, the Ashalim Solar Thermal Power Station will help Israel achieve its goal of having 10% of its electricity production from renewable energy sources by 2020.


Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news