Rebirth of SolarReserve’s 450 MW Likana Brings CSP Supply Chain Hope for Chile

2019.10.31     From: SolarPACES

This week, the Cerro Dominador Group/EIG Global Energy Partners bought the Likana Concentrated Solar Power (CSP) project from US-based SolarReserve, which was unable to complete the project.


SolarReserve had already developed Likana by accomplishing the preliminary work of siting and monitoring local DNI and taking it through Chile’s environmental permitting process, but was unable to complete it. With its financial heft, Cerro Domiador Group/EIG says that it can now begin construction almost immediately and expects to break ground during the first half of 2020.


EIG, the group acquiring Likana is currently completing the 110 MW Cerro Dominador CSP tower project, that it had earlier bought from Abengoa, when it was unable to complete that project. With new funding from EIG, that project is now nearing completion, with Abengoa continuing as EPC, along with Acciona. Both have considerable experience as leaders in Spain’s CSP development, and will have no language barrier working in Chile.


EIG’s new Likana tower CSP project will be built nearby, in the Llano de Quimal sector, 41 km southeast of Calama in the Antofagasta Region. The proposed CSP tower plant will have an installed capacity of 450 MW, making it one of the largest renewable power plants in the country with expected net annual electricity generation of about 3,150 GWh/year.


Previously, the group had announced that they did plan to continue developing additional CSP plants with the same tower technology. This acquisition starts to brings that to fruition. Although the amount of the purchase is still confidential, it is believed that the initiative involves an investment of US $2.4 billion.


SolarReserve originally developed and built a CSP power tower project in the US, the 110 MW Crescent Dunes in Nevada, and was the original developer of South Africa’s Redstone, but was unable to achieve financial close on its Aurora tower project in Australia, and has since refocused on PV projects. It left a permitted development pipeline in Chile that is a potential source of additional CSP tower projects permitted and ready to be built.


Its 450 MW Tamarugal project (contemporaneous interview with then SolarReserve CEO, Kevin Smith) and the 260 MW Copiapó tower CSP that was permitted in 2015. Both broke PPA bid records, but were unable to get contracts.


Likana will consist of three 110 MW towers, with three power blocks – LIK 1, LIK 2 and LIK 3. The transmission line of the project to the sectioning substation will have an extension of about 61.3 km.


Supply chain implications


On completion, together with Cerro Dominador at 110 MW, this will bring Chile’s CSP capacity to over half a gigawatt. During construction, the average workforce that will be needed is 800 workers with maximum of 1,200. Once in operation, the plant will require an average of 40 workers and a maximum of 120.


Such a large jump in CSP implementation will create the impetus for a CSP supply chain in Chile. EIGs financial clout and commitment, plus the extensive pipeline of permitted projects left behind by SolarReserve opens the way to remove the obstacle to CSP in that country.


Unlike the solar farms comprising PV panels which can be readily shipped from abroad, CSP’s more complex thermal power block technology relies on local supply chains for much of a plant.


A paper presented at the SolarPACES Conference in Morocco determined that the biggest barrier to CSP deployment in Chile was potential supply chain wariness of retrofitting assembly lines for a potential CSP demand that might not happen. With EIG’s purchase of Likana at such a large size, bringing total CSP tower capacity to over half a gigawatt, the firm’s vision and ambition puts an end to those concerns.





Upcoming CSP events:


5th CSP Focus MENA 2020(June,Dubai, UAE)

10th CSP Focus China 2020 (March, Beijing China) 


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.

Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news