2017.12.04     From: CSP Focus 光略咨询



As one of China 1st batch 20 pilot CSP projects, Recently, Yumen Xinneng tower CSP project opened the bidding of molten salt earlier this week. The bidding includes: sodium nitrate/ nitrate of potash (6:4); sodium nitrate 9900 tons and potassium nitrate 6600 tons.

 

Two schemes:

Procurementscheme 1: Unmixed molten salt, sodium nitrate 9900 tons (Section 1), potassium nitrate6600 tons (Section 2).

Procurementscheme 2: Mixed molten salt (Section 3), sodium nitrate/ nitrate of potash(6:4), 16500 tons.

 

5 companies participated in the bidding as list as below:


Bidders

Section

Qinghai Enesoon,  China

1, 2, 3

Xinjiang  Nitre Potash Co., Ltd., China

1

BASF,  Germany

1

Qinghai Lianda  Chemical Technology Co., Ltd, China

1, 2

 

Resources say Tthe bidding result will be announced in late December 2017.

Free report: China Yumen Xinneng 50MW Molten Salt Tower CSP Project

Another progress on the Yumen Xinneng 50MW CSP project: The project construction subcontractor, Anhui No.1 Electric Power Construction Co., Ltd announced that the base column pouring has been constructed on schedule. With the effort of all staff, the task has been finished on Nov, 14.


Yumen Xinneng 50MW molten salt tower CSP plant was officially selected as one of China 1st batch of CSP pilot projects in September 2016. With total investment of RMB 1.78 billion, the project is expected to be completed in 2 years. The project is located in Zhengjiashawo CSP Park, 5km far from new downtown of Yumen city, Gansu Province. The 50MW project takes beam-down CSP technology with 15 mirror field modules, and one 9-hour molten salt thermal storage system & steam turbine set. The annual generating capacity is under load of 4328 hours.


As the Owner’s Engineer, Parasol is responsible for the whole scheme design; XinChen CSP provides core components like heliostat, tower and receiver; Thvom offers EPC and conventional island construction services.  


Report download: China Yumen Xinneng 50MW Molten Salt Tower CSP Project Introduction

CSP Focus China 2018 Mar.22-23 Beijing will invite major project developers and core component vendors to explore current status, progress and challenges of Yumen Xinneng 50MW Molten Salt Tower CSP Project as well as other pilot projects. Sincerely invite you to join in the conference and probe into the development of China CSP industry.

Book your seat right now to gain early bird discount SAVE USD300 by registering before Dec.7th

Leave your thoughts here

Free Reports

See more+
  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

  • BrightSource Engineering and Manufacturing System

    Engineering, Supply Chain, Construction, Business Intelligence. What about the Min O&M?

  • Yumen Xinneng 50MW Molten Salt Tower CSP Project

    The project broke ground in June 2017, and 3 of the 15 modules are expected to be connected to the gird by the end of September, 2019. It will be the first large‐scale commercial CSP plant in the world taking innovative beam-down molten salt tower CSP technology.

  • Luneng Haixi 50MW Molten Salt Tower CSP Project

    With total capacity of700MW, Luneng Haixi Geermu Multi-energy Complement Integration OptimizationPilot Project consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energystorage system. Updating--Jan., 2019 Edition1. Overview (P2)2. Highlights (P2)3. Fast sheet (P3)4. Project Milestones (P4)5. Project Participants 5.1. Developer (P5) 5.2. Owner&Investor (P5) 5.3. EPC Contractor (P5)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news