Supcon Solar’s Delingha 50MW CSP Project breaks Monthly Output record
2020.11.10 From: Supcon Solar
After steam turbine overhaul,the plant was recovered to full load operation on October 9, 2020. As of 24:00 on November 8, the total monthly output reached 18.4 GWh, which refreshed prior record in Feb, 2020 (17.17GWh), and exceeded average designed output by 6.23GWh (The plant is designed to generate 146GWh/y, i.e. 12.17GWh/month).
SUPCON SOLAR Delingha 50MW CSP Plant
This year, the collected DNI has undergone sharp fluctuation. In June, the monthly DNI was only 133.6KWh/m²,yet this figure was over 221KWh/ m² in both February and October. From Oct 9 to Nov 8, the collected DNI was 227.39kwh/ m².
During this period (Oct 9 to Nov 8), there were 24 days meeting 90% of theoretical production. In particular, there were 9 days fulfilling over 100%. The total energy delivered to the grid was 17.15GWh with auxiliary power consumption rate of 6.78%, which was also the best record since the plant was put into operation.
SUPCON SOLAR Delingha 50MW CSP Plant
Upcoming CSP events:
11th CSP Focus China 2020 (March, Beijing China)
5th CSP Focus MENA 2020(Time TBA,Dubai, UAE)
More CSP news and reports please visit www.cspfocus.cn
or CSP Focus social media on LinkedIn, Twitter, Facebook.
More from CSP Focus
NextThe UAE secures its place in the sun flexing its PV/CSP muscle
China Royal Tech Yumen 50MW solar CSP PT project calls for steam turbine and generators
Progress|China Shouhang Dunhuang 100 MW molten salt Solar Tower CSP Plant
Concentrated Solar Power will reach 20% of the energy matrix in Chile by 2050
Shouhang and EDF to Test s-CO2 Cycle in Concentrated Solar Power
Andasol I and II concentrated solar power plants in Spain were financed in 2006
Huge 110 MW concentrated solar power tower and storage project begins production in Chile
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower