China Gonghe 50MW Tower solar CSP project biddings open for civil construction of solar field and conventional island

2017.12.18     From: CSP Focus 光略咨询



Power China Qinghai Gonghe 50MW Tower CSP Project is one of China 1st batch 20 pilot CSP projects. The project developer published biddings for civil construction of solar field and conventional island on Dec. 15, and both of the biddings will be opened on Jan 10, 2018. And the construction periods are requested from March 1st to August 31st in 2018.

As CSP Focus reported earlier, the project progress is expected to be:
•    June, 2017, construction officially started;
•    By March 1st, 2018, heliostat manufacturing workshop will be put into operation;
•    By June 1st, 2018, heliostat installation starts;
•    By Dec. 30, 2018, solar field and receiver installation finished;
•    By April, 2019, project completed and connected to the grid.

Relevant free report: Detailed Progress on China 1st Batch 20 CSP Pilot Projects

The solar field construction work includes heliostat base installation, field leveling, electrical equipment foundation construction and relevant equipment installation, solar field cable laying and road construction around solar field.

All civil construction and installation works of conventional island except for receiver tower and heat storage are included in the bidding for conventional island construction.


The bidding announcements indicated that bidders should possess relevant qualification and have over 3 similar projects performance and experience in 3 years. Besides, joint biddings are not allowed.

The project details will be discussed at the upcoming CSP Focus China 2018 Mar.22-23 Beijing conference.

Power China Qinghai Gonghe 50MW Tower CSP Project is owned and developed by Power Construction Corporation of China. Located in Nanzhou Solar Power Park, Qinghai Province, Power China Qinghai Gonghe 50MW Tower CSP Project is designed to have 6 hours molten salt thermal energy storage system. The project construction started on June 18 this year.

Part of participants announced:
●  Supcon Solar (solar field EPC)
●  Harbin Turbine Company Limited (turbine)
●  Shanghai Boiler Co., Ltd. (steam generator)

●  Qinghai Lianda Chemical Co., Ltd. (molten salt)
●  Shanghai Power Civil Construction Company (receiver tower & thermal energy storage system civil work)

●  Qinghai Haiyi Engineering Construction Co., Ltd (dormitory civil work)

Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news