SUPCON Solar Delingha 50MW molten salt tower CSP project recovers construction after winter stop

2018.03.08     From: CSP Focus光略咨询


Supcon Solar Delingha 50MW CSP plant was selected to be one of China 1st batch of CSP pilot projects on September 2016. As the project developer SUPCON Solar announced earlier, the construction work was officially recovered on March 5th after the freezing cold winter. And the project is going to be finished by the end of 2018 as planned.

As CSP Focus reported, SUPCON Delingha CSP project was started in October 2016, and till now the receiver tower has been finished 73.5 meters of the designed height of 180 meters.

Relevant free report: Status of 50MW project and O&M experience learnt from 10MW pilot project of SUPCON SOLAR



To secure the project quality, the construction work had to be suspended due to the low temperature of -20℃. In the future, the CSP plant will be constructed on schedule as below:


  • June, 2018, tower completed;

  • August, 2018, solar field completed;

  • October, 2018, all project installation to be finished and start commissioning;

  • December, 2018, to be connected to the grid;

  • February, 2019, stably operational.


To get the project detailed progress and experience, you are welcome to join the upcoming CSP Focus China 2018 conference on March 22-23 in Beijing, when Mr. Jin Jiaxiang, Chairman of SUPCON Solar will make key-note speech on the project.

Part of Project Participants of SUPCON Solar Delingha 50MW molten salt tower CSP project


  • Developer & EPC: SUPCON Solar

  • Electricity contractor: STATE GRID QINGHAI ELECTRIC POWER COMPANY

  • Molten salt heat absorption system: HANGZHOU BOLIER GROUP CO, LTD.

  • Steam generator: Hangzhou Steam Turbine Co., Ltd.

  • Tracking system Reducer (13000sets): Jiangyin Huafang New Energy Co., Ltd

  • Slewing Drive (partial): Sunslew


Project Database: SUPCON Solar Delingha 50MW molten salt tower CSP project


Relevant CSP Conference:2018 CSP Focus Conference(March 22-23 Beijing)

Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news