Why Shanghai Electric won EPC contract for Dubai 700MW concentrated solar power project?

2018.04.17     From: CSP Focus光略咨询


Shanghai Electric, a Chinese leading energy and manufacturing corporation, was officially awarded the EPC contract for Dubai 700MW CSP Phase 4 of the Mohammed bin Rashid Al Maktoum Solar Park earlier on April 13th in Shanghai, China. With the total investment of USD 4 billion, the Dubai 700MW CSP plant is the world biggest CSP project.


 


Obviously, the “star” Dubai CSP project is catching the eyes of global energy industry players. When asked about the reasons why it was ACWA Power and Shanghai Electric consortium winning the project, Mr. HE Saeed Mohammad Ahmad Al Tayer, Managing Director & CEO of Dubai Electricity & Water Authority (DEWA) explains, “Firstly, both ACWA Power and Shanghai Electric own the most advanced technology and quite experienced in energy sector, and secondly, the price they offer, USD 7.3 cents/kWh, is quite competitive for cost control.”


To get the newest information of Dubai 700MW CSP project and communicate with the project key players, you are welcomed to join the upcoming CSP Focus MENA 2018 event in Marrakech, Morocco during June 27-28, which will be the can’t missing gathering for CSP industry players watching Middle East & North Africa region. 


Mr. Zheng Jianhua, Chairman of Shanghai Electric Group says, “Thanks to long-term and careful preparation, Shanghai Electric is able to win the world biggest CSP plant though facing quite fierce competition. The success of taking the Dubai 700MW CSP project shows great power of Chinese energy companies like Shanghai Electric.”

 


Overview of Dubai 700MW CSP Project 


Capacity: 700MW in total, 1*100MW molten salt tower plant + 3*200MW thermal oil parabolic trough plants


Thermal Energy Storage: 15-hours molten salt thermal energy storage for each plant


Tower: 260 meters high


PPA: USD 7.3 cents/kWh for 35 years


Total Investment: USD 3.86 billion/ AED 14.2 billion (51% from DEWA, 49% from ACWA Power and China Silk Road Fund)


Project owner: DEWA


Off-taker: DEWA


Developer: ACWA Power


EPC: Shanghai Electric


Tower Technology: BrightSource Energy


Parabolic Trough Technology: Abengoa Solar


Operation: NOMAC, ACWA Power


Free report: Cost Control & Supply Chain Optimization for Dubai 700MW CSP Project by Shanghai Electric


Mr. Zheng Jianhua confesses that the project, as the world “biggest” and “tallest”, is really a great challenge and will inevitably face some problems and risks. At the same time of reaching “the best”, the project should also be completed in time so as to produce power for the Dubai EXPO in 2020.


However, Zheng continues, “We made sufficient evaluation on the potential challenges and risks, and was confident to offer such a low price. Frankly speaking, making profit is not the priority, from the perspective of strategy, we would like to establish the brand in Middle East, so as to get more opportunities in future similar projects. ”


The Dubai CSP project awards Shanghai Electric the 1st EPC contract in big-scale energy sector, and a milestone for Shanghai Electric, a representative of Chinese high-level manufacturers, to step into renewable energy. 


Relevant CSP Conference:CSP Focus MENA 2018(June 27-28,Marrakeck Morocco)

Comments

  • Company''s attitude towards contract is positive,so it will be very beneficial to the company in future.

Leave your thoughts here

Free Reports

See more+
  • Luneng Haixi 50MW Molten Salt Tower CSP Project

    With total capacity of700MW, Luneng Haixi Geermu Multi-energy Complement Integration OptimizationPilot Project consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energystorage system. Updating--Jan., 2019 Edition1. Overview (P2)2. Highlights (P2)3. Fast sheet (P3)4. Project Milestones (P4)5. Project Participants 5.1. Developer (P5) 5.2. Owner&Investor (P5) 5.3. EPC Contractor (P5)

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Overview of Saudi Arabia's Renewable Energy Program 2030

    Saudi Arabia significantly increased its renewable energy targets and long term visibilityMEIM and PIF are working on complemenrary tracks to promote localization of manufacturing5 wind and 3 solar segments can potentially be localized in the short to medium term in KSAProjects will be deployed in 35+ parks spead across the KingdomParks are being pre-developed to boost projects bankability and ex

  • China 1st Batch of CSP Pilot Projects Update

    Nov-2018 Edition Part 1: Background and Fact Sheet(P1) 1.1 Technologies of China CSP Pilot Projects (P2) Chart 1: Technologies of China CSP Pilot Projects (P3) 1.2 Locations of China CSP Pilot Projects (P5) Chart 2: Locations of China CSP Pilot Projects (P6) 1.3 Ownership of China CSP Pilot Projects (P7) Chart 3: Ownership of China CSP Pilot Projects (P8) 1.4 Developer, EPC Contractor and Technology Provider (P9) Chart 4: Developer, EPC Contractor and Technology Provider of China CSP Pilot Projects (P10)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news