Hybrid power project combines concentrated solar power with CCGT
2023.04.12 From: helioscsp
Saudi Electricity Company’s (SEC) Green Duba Integrated Solar Combined Cycle (ISCC) Power Plant, located in Duba in Tabuk province, is expected to be completed by the third quarter of 2023.
“The Operation and Maintenance (O&M) assessment work is currently in progress and the project is expected to be ready by early third quarter 2023,” a source aware of the project details told Zawya Projects.
The solar-gas hybrid power plant [Duba Al-Khadra] integrates thermal solar – concentrated solar power (CSP) – with combined cycle gas turbines (CCGT).
In its 2022 Annual Report, SEC had highlighted that a 260 MW steam unit of the plant was connected to the grid. In August 2021, local newspaper Arab News had reported that the 3.4 billion Saudi riyal project ($907 million) was 95 percent complete.
The Green Duba ISCC Plant will have a total capacity of 605 MW, according to SEC’s 2021 ESG Report. The project’s combined cycle power output was put at 565 megawatts (MW) and that of the solar field at 40MW by SBP Germany which supplied the parabolic troughs for the project. Spain’s IM Energy was the contractor for the CSP plant.
The Spanish-Saudi consortium of INITEC Energia and SSEM (Saudi Services for Electro Mechanic Works) was awarded the SAR 2.5 billion ($666 million) construction contract for the project in 2015 with work starting in 2016. Saudi’s Al Baraka Construction Company was the sub-contractor.
In its press statement dated January 2014, GE had announced that it would supply the engineering equipment package for the combined-cycle plant, including two F-class gas turbines, a 7F.05 and a 7F.03; steam turbine; generators; heat recovery steam generators (HRSG); condenser; boiler feed pumps; distributed control system and a long-term service agreement. The statement said the project also marks the first introduction of condensate as a gas turbine fuel.
In March 2016, ABB announced that it was awarded a $26 million contract to supply 420-kilovolt (kV) Gas Insulated Switchgear (GIS) for the project’s substation.
Writing by Senthil Palanisamy; Editing by Anoop Menon, zawya.com
More from CSP Focus
NextHydrophilic disc uses solar power to separate salt from water
The World Bank Group will no longer finance upstream oil and gas, after 2019.
Oman plans a solar power project that may adopts CSP with capacity ranging from 500-1000MW
EBRD grants €45 million loan for Noor Midelt I concentrated solar power project
Indigenously made solar grade parabolic trough mirrors by Indian Thermosol Glass
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower