China-backed $4bn CSP project set for financial close by August

2018.05.04     From: newenergyupdate

Shanghai Electric will leverage its supply chain capabilities to install the 700 MW plant in Dubai. The plant will use parabolic trough and tower technology. (Image credit: DEWA.)


Developer ACWA Power has now signed key PPA and EPC agreements for the 700 MW plant in Dubai while Chinese partner Shanghai Electric has started optimization activities along the supply chain, project partners told the MENA New Energy 2018 conference.


Last month, Saudi Arabia’s ACWA Power signed an Engineering, Procurement, and Construction (EPC) contract with Shanghai Electric, a major Chinese power company, to install its 700 MW DEWA CSP project in Dubai.


The 700 MW dual-technology CSP project, awarded by the Dubai Electricity and Water Authority (DEWA) in September 2017, sets a new industry record for size and cost-efficiency.


The project will require 14.2 Billion AED ($3.9 billion) in investment and will consist of three 200 MW parabolic trough systems and a 100 MW central tower plant. The project was awarded at a tariff price of $73/MWh and includes up to 15 hours of energy storage capacity.


Spain’s Abengoa and U.S. developer BrightSource are the respective technology providers for the parabolic trough and central tower plants, bringing decades of CSP industry experience to the project.


Project documents, including the power purchase agreement (PPA) with DEWA and EPC contracts, have now been signed and talks with financial lenders are at a "very advanced stage," Meriem Bellizim, ACWA Power’s project manager for the DEWA 700 MW CSP project, told the conference on May 24.


Industrial and Commercial Bank of China (ICBC) is mandated lead arranger for a $1.5 billion senior loan. ICBC, Bank of China and Agricultural Bank of China will together provide almost 80% of senior debt.


Financial partners-- which involve local, and international investors including Chinese groups-- are currently working through conditions precedent, Bellizim said.


"Financial close will be around the end of July, maybe the beginning of August," she said.


China installs


A key driver of the low tariff is a 35-year PPA provided by DEWA, much longer than the typical 20 to 25 years offered for CSP projects to date, which spreads the initial investment across a longer period and reduces the annual cost of capital.


Economies of scale and purchasing power will also play a major role. The construction of three 200 MW parabolic trough systems will allow manufacturers to introduce economies of series.


Shanghai Electric's experience as a plant supplier as well as an EPC contractor will allow it to drive for efficiencies in the supply chain, Bellizim said.


Shanghai Electric is one of China's top five power generators. Owned by China Power Investment Corporation, Shanghai Electric has a total installed capacity of 107 GW, including 5 GW of solar power and 10 GW of wind. The company is active in 35 countries.


In 2014, Shanghai Electric and BrightSource formed a joint venture (JV) for the construction of utility-scale CSP plants in China. The JV combined BrightSource's solar tower technology and installation experience with Shanghai Electric's EPC and supply experience.


The JV between Shanghai Electric and BrightSource includes the construction of a 135 MW tower with molten salt storage at the Huanghe Qinghai Delingha project in Qinghai province, selected under China's 1.35 GW CSP Commercial Demonstration Pilot Program. The partners plan to build multiple 135 MW towers at the site.


The JV has helped improve the efficiency of the central tower design and supply chain and has reduced costs, Wang Deyuan, Associate Managing Director - Integrity Energy Solution Business Unit at Shanghai Electric, told the conference.


Shanghai Electric has worked with BrightSource to optimize the installation of central tower solar fields, including mirrors, molten salt receivers, and control systems, and these learnings can be applied to the Dubai project, Deyuan said.


"The combination between BrightSource and Shanghai Electric could benefit the integrated solution- especially for the solar field," he said.


Work underway


ACWA Power has issued a limited notice to proceed (LNTP), allowing Shanghai Electric to move forward with supply optimization ahead of a full NTP later this year.


Early preparations for installation will help reduce project risk, Deyuan said.


"All kinds of experience and lessons learned will be helpful for us to understand the challenges," he said.


For the parabolic troughs plant, Shanghai Electric is collaborating with Abengoa to find innovative solutions to best integrate the solar field and power block, Deyuan said.


Maximizing overall plant performance is a priority for Shanghai Electric, he said.


"We will mix best practice from the past experience...And continue to optimize the solutions. We found there are a lot of spaces to be improved.”


Shanghai Electric will look to optimize all aspects of the supply chain, including raw materials costs, Deyuan said.


"We have a huge demand of quantity for the materials and equipment...We would like to have open discussions...for collaboration with participators for this project, to find the best solutions," he said.


Supply chain gains for the DEWA project should help support global CSP growth and the buildout of a “very strong supply chain” in the Middle East, Deyuan said. Other projects up for tender in the Middle East and North Africa (MENA) region include Morocco's 800 MW Midelt project hybrid PV-CSP project, for which contracts are expected to be allocated in 2018.


 MENA CSP pipeline in 2018


 (Click image to enlarge)



Source: Middle East Solar Industry Association's (MESIA) 'Solar Outlook Report 2018.'

 

Lessons learned will also encourage the further development of the Chinese CSP market, Deyuan said.


China’s Demonstration Pilot CSP program will support the growth of a domestic CSP industry, and installation and technology experience gained from abroad will allow China to diversify its technology base, he said.


"This will give us more chances to achieve technology improvements," Deyuan said.


Falling costs


Michael Geyer, Vice President Business Development at Abengoa, said lower CSP costs are possible in the coming years.


Increasing efficiency of heat transfer fluids, improvements in receivers and collectors, and automation of manufacturing and operations and maintenance activities should all drive down costs, Geyer said.


"There is still lots of room for improvement for automating the O&M," he noted.


A CSP plant of capacity 100 MW-150 MW might typically have around 50 to 70 operational staff, and this number could be significantly reduced with automation, Geyer said.


"There is much less automation in these plants than we have in....combined cycle [gas] or coal plants," he said.


"The important condition here is that there is a continuous pipeline of projects...DEWA is an important step, China will be important step," Geyer said.


New Energy Update


Relevant CSP Conference:CSP Focus MENA 2018(June 27-28,Marrakeck Morocco)

Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news