Onsite pictures--China Supcon Delingha 50MW Tower CSP plant

2018.08.20     From: CSP Focus


 

Amongst China 1st batch of CSP demonstrations, SUPCON Solar Delingha 50MW CSP plant takes molten salt central tower technology with 7 hours' thermal electricity storage system. A total number of 27,135 heliostats (20 square meter) will be installed for the project.


As Mr. Jin Jianxiang, Chairman of SUPCON Solar told CSP Focus, recently the project team are quite busy with the onsite installation. The central receiver will be completed with 32 pieces, of which 28 pieces have been transported to the project venue and the other 5 (one is for backup) are one the way.


The picture below shows the steel structure for hanging central receiver:



Receiver pieces onsite readay for installation


July 2013, SUPCON built 10MW tower CSP project in Delingha, which is the first commercial CSP tower project in China and the third in the world. Molten salt renovation was finished on Aug. 2016. Over 95% core equipment was make in China, which broke the monopoly of overseas molten salt CSP tower project core technology and it was a great milestone of CSP technology localization.


The 50MW project will be finished by the end of this year and achieve stable output in February 2019.


Free Report: Power Output Reduction Caused by Equipment Accidents---Supcon 10+50MW CSP Tower CSP Plant Case Study


 Supcon Solar Delingha 10MW+50MW Solar CSP Tower Plants

 


Heliostats of Supcon 10MW CSP Tower Plant



Heliostats of Supcon 50MW CSP Tower Plant


Free Report: Suppliers List of China Key CSP Projects (including Supcon 50MW CSP Tower Plant)



Steam Turbine of Supcon 50MW CSP Tower Plant



More information on Supcon CSP plant and technology innovation, you are also welcome to join the upcoming CSP Focus Innovation 2018(Oct.25-26, Xi'an, China), when Mr. Jin Jianxiang, Chairman of Supcon Solar will make detalied presentations. Other speakers together with Mr. Jin are excutives from Abengoa, TSK, BrightSource, Shanghai Electric, Northwest Electric Power Design Institute, sbp sonne gmbh...Click to see the speaker list.




Click to get brochure of CSP Focus Innovation 2018(Oct.25-26, China)and register before Aug.23 to SAVE USD 200.


Leave your thoughts here

Free Reports

See more+
  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

  • BrightSource Engineering and Manufacturing System

    Engineering, Supply Chain, Construction, Business Intelligence. What about the Min O&M?

  • Yumen Xinneng 50MW Molten Salt Tower CSP Project

    The project broke ground in June 2017, and 3 of the 15 modules are expected to be connected to the gird by the end of September, 2019. It will be the first large‐scale commercial CSP plant in the world taking innovative beam-down molten salt tower CSP technology.

  • Luneng Haixi 50MW Molten Salt Tower CSP Project

    With total capacity of700MW, Luneng Haixi Geermu Multi-energy Complement Integration OptimizationPilot Project consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energystorage system. Updating--Jan., 2019 Edition1. Overview (P2)2. Highlights (P2)3. Fast sheet (P3)4. Project Milestones (P4)5. Project Participants 5.1. Developer (P5) 5.2. Owner&Investor (P5) 5.3. EPC Contractor (P5)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news