No.1-5 Modules to be finished late December of China Yumen Xinneng 50MW Beam-down tower CSP Project
2018.09.11 From: CSP Focus
Yumen
Xinneng 50MW molten salt tower CSP plant was officially selected as one
of China 1st batch of CSP pilot projects in September 2016, and it has been developed and constructed rapidly since the the break-ground on June 8th, 2017.
It is expected that No.1-5 Modules will be completed and connected to the grid at the end of this year in 2018.
It is the only pilot project taking innovative beam down CSP tower technology. With total investment of RMB 1.79 billion, Yumen Xinneng 50MW molten salt tower CSP project is made of 15 mirror field Modules, and each module consists of 17MWth solar filed and one beam-down tower, totaling 50MWe. Also one 9-hour molten salt thermal storage system & steam turbine set are included in the project.
As of today, No.1 Module has been fully completed; Tower of No.2 Module is built up, and 357 heliostats finished; Tower of No.3 Module has been 30% installed; No.4-10 Modules are under construction.
The central cold and hot molten salt tanks have been ready for the whole project.
Free Report: Yumen Xinneng 50MW Molten Salt Tower Beam-down CSP Project
Take a look on the development and progress:
● December, 2018, No.1-5 Modules to be completed and connected to the grid.
● June, 2018, No.1 Module completed, heliostats installation finished.
● April, 2018, steam turbine foundation started, and No.2-5 modules started construction.
● Dec.7, molten salt thermal electricity storage system started construction.
● Dec. 4, 2017, heat exchanger bidders announced & steam generator bidding restarted.
● Nov. 28, 2017, molten salt bidding opened.
● 2017, the first solar collecting system module commissioning to be finished.
More details on the project, please visit:
CSP Focus database: Yumen Xinneng 50MW Molten Salt Tower Beam-down CSP Project
Xinchen CSP Technology Co.,Ltd works in the project as technology provider, and solar field and thermal storage system integrator. Mr. Chen Yuda, General Manager of Xinchen CSP will lead a team to present upcoming CSP Focus Innovation 2018(Oct.25-26, China) conference, where you may get more fresh news on the project and technological innovations on CSP system and key components.
Click to get brochure of CSP Focus Innovation 2018(Oct.25-26, China) and register before Sept.20 to SAVE USD 100.
More from CSP Focus
NextShams continues to contribute to UAE’s clean energy transition
CSP hybridization projects on the new world energy landscape
Cloud camera system WobaS provides concentrated solar power plants with reliable radiation nowcasts
Hi-Temp Concentrating Solar Power On Mars!? Tell Us Why — Or Why Not (CT Exclusive Interview)
The solar thermal could fall to 45 euros / MWh in 2020 for some Concentrated Solar Power projects
Luneng Haixi 50MW molten salt tower CSP project to operate this June
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower