Phase 4 Of Dubai's MBR Solar Park 700MW Registers Progress

2018.09.22     From: utilities-me.com

Phase 4 of the project marks the world's largest investment in a concentrated solar power (CSP) plant, and Dewa's Saeed Mohammed Al Tayer recently toured the project site.


The Concentrated Solar Power (CSP) park is being built in Dubai. It is the fourth phase of the Mohammed Bin Rashid Al Maktoum solar park with a capacity of 700MW


The development progress of Dubai's Mohammed bin Rashid Al Maktoum Solar Park (MBR Solar Park) 700-megawatt (MW) Phase 4 has been inspected by the managing director and chief executive officer of Dubai Electricity and Water Authority (Dewa). 


Phase 4 of the project marks the world's largest investment in a concentrated solar power (CSP) plant, and Dewa's Saeed Mohammed Al Tayer recently toured the project site. 


An engineering, procurement, and construction contract for the $3.9bn (AED14.2bn) fourth phase was signed this April between Saudi Arabia-headquartered co-developer ACWA Power, and China-based Shanghai Electric, which is acting as the project’s main contractor.


MBR Solar Park is a critical element of Dubai Clean Energy Strategy 2050, and will have a total capacity of 5,000MW by 2030. Investments in the project are expected to total $13.6bn (AED50bn), and the project will support Dubai's shift towards solar energy. 


Al Tayer was briefed on the project by Abdul Hamid Al Muhaidib, executive managing director of Noor Energy 1, which was launched by Dewa, Acwa Power, and China's Silk Road Fund. 


During his tour of the site, Al Tayer stressed on the need to complete the project in line with the highest health, safety, and quality standards, as well as on time. 


MBR Solar Park is the world's largest single-site facility of its kind to be based on the independent power producer model. Phase 1 of the project, with a photovoltaic (PV) capacity of 13MW, commenced operations in 2013, while its PV Phase 2, with a capacity of 200MW, was launched in March 2017. 


The 800MW Phase 3, also using PV tech, will be operational by 2020, and the first stage of the CSP Phase 4 will be commissioned in Q4 2020, WAM reported.


Relevant CSP Conference: CSP Focus Innovation 2018(Oct.25-26, Xi'an, China.)

Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news