中文  |  ENGLISH

150MW NOORo III Parabolic Trough CSP Project

<BACK

   2019-4-8


Project Schedule


 ● October, 2018, Project completed 

 ● September, 2018, Operation in full load

 ● June, 2018, Commissioning started

 ● March, 2018, Receiver installation completed

 ● November 27th, 2017, Auxiliary power receiving successed

 ● August, 2017, Steam Turbine installation completed

 ● May 29th, 2017, Generator installed

 ● May 18th-22th, 2017, SGS installation completed

 ● April 25th, 2017, Deaerator installed

 ● April, 2017, Main transformer installed

 ● March, 2017, DCS power receiving successed

 ● October 13th, 2016, Tower concreting completed

 ● May, 2015, Financial closed

 ● May 8th, 2015, SEPCO3 signed EPC contract with ACWA Power

Full report (Member Only)


Project Overview


Located in Ouarzazate Morocco, NOOR Ouarzazate (NOORo) is one of the biggest solar energy complex in the world. Consisting of four phases, NOORo project is part of Moroccan Renewable Energy Plan, which aims to 42% of RE installed capacity in national energy mix in 2020, and 52% in 2030 in Morocco. The NOORo I, II and III are CSP projects, with total capacity of 510MW, and the fourth NOORo IV is a 72MW PV project.


Apply CSP Focus Membership to see full report


Project Participants

    

Apply CSP Focus Membership to see full report

                                                                                                                                                                                                                               

 Plant photos




Latest News

See more+
  • Dubai’s concentrated solar power project starts supplying electricity to the grid

    On November 29 (Dubai Time), the Trough Unit No. 1 facility of Shanghai Electric’s 700MW solar thermal and 250MW photovoltaic solar power plant in Dubai has successfully achieved grid-connected electricity generation, marking a significant milestone along the path of the firm’s entry into the renewable energy sector. The facility is already delivering top-notch technical parameters and reliable

  • Four bidders shortlisted for 200MW solar plant

    The plant, which will use lenses or mirrors to focus a large area of sunlight onto a receiver, is due to be operational by 2027 and is the flagship renewable project in government’s Integrated Resources Plan (IRP) for energy development in the years to 2040.On Tuesday, the Ministry of Minerals and Energy published a shortlist of four bidders who include major global players with thousands of mega

  • CSP Project Tenders Last Week (Nov.14-20)

    Project Construction Supervision Bidding- POWERCHINA Ruoqiang 100MW CSP + 900MW PV ProjectOn Nov. 14, POWERCHINA Renewable Energy Co., Ltd issued a tender announcement for the construction supervision of the POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project. According to the announcement, the owner of POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project is POWERCHINA Ruoqiang Ruida Energy Development C

  • CSP Project Tenders Last Two Week (Nov. 1-13)

    Vacuum Pump Tender- Akesai Huidong New Energy CSP + PV Pilot ProjectOn November 7, East China Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group issued a procurement announcement for vacuum pumps for the Akesai Huidong New Energy CSP + PV Pilot Project.Latest Milestone- Akesai Huidong New Energy CSP + PV Pilot ProjectAccording to the Aksai County Government, the

Reports(Member Only)

See more+

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news