Hami 50 MW CSP Project

<BACK

   2020-1-14


 Project Schedule



   2019-12-29, successfully connected to the grid

  ● 2018-11-19, project installation started    New!  

  ● 2018-10-26, structure of the 180m receiver tower completed

  ● 2017-10-19, project construction started

  ● 2017-9-28, approval of project basic engineering

  ● 2016-12-16, project starting ceremony held in Hami

  ● 2016-8-11~12, inspection discussion on Project Feasibility Study held in Hami


 Full report view online


 Project Overview


Enlisted in China CSP Pilot Projects, CPECC Hami 50MW Tower CSP Project was located in Naomaohu Town, Yiwu County, Hami,Xinjiang.

 

With planned capacity 2*50MW, the phase one of 50MW will use molten salt tower technology, and the construction period was estimated to be 21 months.


Basic Information

Location

Naomaohu Town, Yihu County, Hami

DNI

2015.3kWh/m2/year

Installed Capacity

50MW

Technology

Molten Salt Tower CSP

Heliostat

Stellio

Storage

13 Hours

Weight of Molten Salt

16920 Mt

Photoelectric Efficiency

15.50%

Water Consumption

0.0986 m3/s.GW

Starting Date

19 Oct, 2017

Status

Under Construction

COD

2019 (expected)

Annual Electricity Generation

198.3 GWh (expected)

Total Investment

RMB 1.58 Billion

IRR

>10%


Project Participants

               

Equipment

Bidders (Winners  are highlighted)

EPC Contract

NWEPDI

Steam Tuibine

Shanghai Turbine Works Co., Ltd.

Dongfang Turbine Co., Ltd

Harbin Turbine Co., Ltd

Hangzhou Steam Turbine Co., Ltd

Qingdao Jieneng Steam Turbine / MAN

SGS

Shandong Beichen

Hangzhou Boiler Group

Jiangsu Shuangliang Boiler Co., Ltd

Harbin Turbine Co., Ltd

Harbin Boilor Co., Ltd

Dongfang Boilor Co., Ltd

Jiangsu Livo New Energy

Power Generator

Harbin Electric Company

Wolong ELectric Group Co.,Ltd

Dongfang Electric Co., Ltd

Shanghai Electric Co., Ltd

Shandong Jinan Power Equipment  Factory

Solar Field and Central Receiver

Beijing Shouhang IHW Resource  Saving Co., Ltd

Zhejiang Supcon Solar Energy  Technology

Shanghai Electric BrightSource

SEPCO 3

Dongfang Boilor Co., Ltd

Harbin Turbine Co., Ltd

SGS Molten Salt Circulating Pump

Ruhrpumpen China

Suzhou Sulzer Pump

Flowserve Flow Control Suzhou

Aliaxis

Molten Salt Thermostat pump

Jiangsu Feiyue Machine and Pump  Group

Jiangsu Jinlin Chemical Machinery  Co., Ltd

Jinan Warwick Pump Co., Ltd

Suzhou Sulzer Pump

Beijing Power Equipment Group

Molten Salt Tank

Bluestar Beijing Chemical Machinery  Co., Ltd

Molten Salt Tank Electric Heater

Chromalox

DCS

Nanjing Sciyon Automation Group  Co., Ltd

Potassium Nitrate

Jiaocheng Bingsheng Chemical

Heat Tracing - Receiver System

Chromalox

Heat Tracing

Bartec

DCS Stimulator

State Nuclear Power Automation  System Engineering

                                                                                                                                                                            

 Plant photos






More from CSP Focus

Next

Latest News

See more+
  • EPC and Project Supervisor Tendering - Guazhou 700MW CSP+PV+Wind

    June 2022Three Gorges Hengji Nengmai Guazhou 700MW CSP+PV+Wind Project was part of the 1.3GW CSP projects released last year in China. The project feasibility study was reviewed and approved in Feb 2022. The project developer issued the tender of EPC by the end of April and tender Project Supervisor 5th of May.Project HighlightsThe Project is consisting of 200MW PV, 400MW Wind and 100MW CSP, and t

  • Construction Started - 100MW CSP of Jinta Zhongguang Solar Energy

    June 17th. Jinta County, Gansu Province. Jinta Zhongguang Solar Energy 100MW CSP project started the concrete grouting for the receiver tower foundation, which was a grand milestone for the construction of the project.The 100MW CSP project was enrolled as the first round of pilot projects back to 2016. But the original developer, China Three Gorges New Energy failed to start the project. Cosin Sol

  • Acciona trusts again in the concentrated solar power in Spain: it will build a hybrid project with photovoltaic in Badajoz

    Acciona Energy and solar thermal have always gone hand in hand. Not only in our borders, but has also taken this technology to other markets such as Chile, South Africa, etc.In 2018, it got rid of the five plants it owned in Spain and sold the 250 MW of concentrated solar power to CountourGlobal for just over 1,000 million euros.Well, now Acciona returns to solar thermal energy in Spain. And it do

  • Vast Solar agrees joint venture with 1414 Degrees to progress Port Augusta project

    Vast Solar is pleased to announce it will be co-developing the Aurora Energy Project (Aurora) through its acquisition of 50% of the shares in Silicon Aurora Pty Ltd (Silicon Aurora) from 1414 Degrees (14D) for $2.5 million.

Reports(Member Only)

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project (Member Only)

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update (Member Only)

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating) (Member Only)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project (Member Only)

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)