Hami 50 MW CSP Project
<BACK2020-1-14
Project Schedule |
● 2019-12-29, successfully connected to the grid ● 2018-11-19, project installation started New! ● 2018-10-26, structure of the 180m receiver tower completed ● 2017-10-19, project construction started ● 2017-9-28, approval of project basic engineering ● 2016-12-16, project starting ceremony held in Hami ● 2016-8-11~12, inspection discussion on Project Feasibility Study held in Hami |
Project Overview |
Enlisted in China CSP Pilot Projects, CPECC Hami 50MW Tower CSP Project was located in Naomaohu Town, Yiwu County, Hami,Xinjiang.
With planned capacity 2*50MW, the phase one of 50MW will use molten salt tower technology, and the construction period was estimated to be 21 months.
Basic Information | |
Location | Naomaohu Town, Yihu County, Hami |
DNI | 2015.3kWh/m2/year |
Installed Capacity | 50MW |
Technology | Molten Salt Tower CSP |
Heliostat | Stellio |
Storage | 13 Hours |
Weight of Molten Salt | 16920 Mt |
Photoelectric Efficiency | 15.50% |
Water Consumption | 0.0986 m3/s.GW |
Starting Date | 19 Oct, 2017 |
Status | Under Construction |
COD | 2019 (expected) |
Annual Electricity Generation | 198.3 GWh (expected) |
Total Investment | RMB 1.58 Billion |
IRR | >10% |
Project Participants |
Equipment | Bidders (Winners are highlighted) |
EPC Contract | NWEPDI |
Steam Tuibine | Shanghai Turbine Works Co., Ltd. |
Dongfang Turbine Co., Ltd | |
Harbin Turbine Co., Ltd | |
Hangzhou Steam Turbine Co., Ltd | |
Qingdao Jieneng Steam Turbine / MAN | |
SGS | Shandong Beichen |
Hangzhou Boiler Group | |
Jiangsu Shuangliang Boiler Co., Ltd | |
Harbin Turbine Co., Ltd | |
Harbin Boilor Co., Ltd | |
Dongfang Boilor Co., Ltd | |
Jiangsu Livo New Energy | |
Power Generator | Harbin Electric Company |
Wolong ELectric Group Co.,Ltd | |
Dongfang Electric Co., Ltd | |
Shanghai Electric Co., Ltd | |
Shandong Jinan Power Equipment Factory | |
Solar Field and Central Receiver | Beijing Shouhang IHW Resource Saving Co., Ltd |
Zhejiang Supcon Solar Energy Technology | |
Shanghai Electric BrightSource | |
SEPCO 3 | |
Dongfang Boilor Co., Ltd | |
Harbin Turbine Co., Ltd | |
SGS Molten Salt Circulating Pump | Ruhrpumpen China |
Suzhou Sulzer Pump | |
Flowserve Flow Control Suzhou | |
Aliaxis | |
Molten Salt Thermostat pump | Jiangsu Feiyue Machine and Pump Group |
Jiangsu Jinlin Chemical Machinery Co., Ltd | |
Jinan Warwick Pump Co., Ltd | |
Suzhou Sulzer Pump | |
Beijing Power Equipment Group | |
Molten Salt Tank | Bluestar Beijing Chemical Machinery Co., Ltd |
Molten Salt Tank Electric Heater | Chromalox |
DCS | Nanjing Sciyon Automation Group Co., Ltd |
Potassium Nitrate | Jiaocheng Bingsheng Chemical |
Heat Tracing - Receiver System | Chromalox |
Heat Tracing | Bartec |
DCS Stimulator | State Nuclear Power Automation System Engineering |
Plant photos |
More from CSP Focus
NextLatest News
See more+-
SUPCON SOLAR Delingha 50MW Molten Salt Tower CSP Plant Passed the Technical Assessment of Fichtner
Recently, Delingha 50MW Molten Salt Tower CSP Plant, constructed by Zhejiang SUPCON SOLAR Technology Co., Ltd. (SUPCON SOLAR), has passed complete technical assessment of Fichtner, a German independent engineering consultancy company. In the assessment report, Fichtner considers the design of the plant corresponds to state-of-the-art design of similar plants in the world, the self-developed helios
-
New Azelio Installation at Khalifa University’s Masdar Institute Solar Platform to Demonstrate Renewable Energy 24/7
Using a recycled aluminium alloy to store the heat from the day’s sunshine allows the MISP to produce electricity 24/7 The world is moving continuously towards using sources of energy that are more sustainable than the fossil fuels on which we predominantly rely today. Solar power is one of the most promising renewable energy technologies, especially in the UAE, allowing the generation of electri
-
Cubico Sustainable Investments refinances 100 MW of CSP in Spain with green loans
Cubico Sustainable Investments (Cubico), a leader and global investor in renewable energy, has achieved financial close on the refinancing of the Andasol I and Andasol II concentrated solar power (CSP) projects in Granada, Spain.The refinancing of the projects, which were acquired in 2017 and have a capacity of 50 MW each, was completed with two green loans.The green loans comply with the Green Lo
-
US CSP valve leap boosts prospects for hotter plants
New flow control valves being developed by US researchers could help CSP developers meet ambitious cost reduction targets.Sandia National Laboratories has partnered with global valve and pump group Flowserve and nuclear power developer Kairos Power to develop valves that can withstand far higher temperatures than current designs. The valves feed a heat transfer medium (HTM) - typically molten salt
Free Reports
See more+-
Dubai 950MW NOOR Energy 1 CSP+PV Project
The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.
-
China Large-scale CSP Projects Update
Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch
-
Suppliers List of China Key CSP Projects (Updating)
13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C
-
Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project
40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)