Hami 50 MW CSP Project

<BACK

   2020-1-14


 Project Schedule



   2019-12-29, successfully connected to the grid

  ● 2018-11-19, project installation started    New!  

  ● 2018-10-26, structure of the 180m receiver tower completed

  ● 2017-10-19, project construction started

  ● 2017-9-28, approval of project basic engineering

  ● 2016-12-16, project starting ceremony held in Hami

  ● 2016-8-11~12, inspection discussion on Project Feasibility Study held in Hami


 Full report view online


 Project Overview


Enlisted in China CSP Pilot Projects, CPECC Hami 50MW Tower CSP Project was located in Naomaohu Town, Yiwu County, Hami,Xinjiang.

 

With planned capacity 2*50MW, the phase one of 50MW will use molten salt tower technology, and the construction period was estimated to be 21 months.


Basic Information

Location

Naomaohu Town, Yihu County, Hami

DNI

2015.3kWh/m2/year

Installed Capacity

50MW

Technology

Molten Salt Tower CSP

Heliostat

Stellio

Storage

13 Hours

Weight of Molten Salt

16920 Mt

Photoelectric Efficiency

15.50%

Water Consumption

0.0986 m3/s.GW

Starting Date

19 Oct, 2017

Status

Under Construction

COD

2019 (expected)

Annual Electricity Generation

198.3 GWh (expected)

Total Investment

RMB 1.58 Billion

IRR

>10%


Project Participants

               

Equipment

Bidders (Winners  are highlighted)

EPC Contract

NWEPDI

Steam Tuibine

Shanghai Turbine Works Co., Ltd.

Dongfang Turbine Co., Ltd

Harbin Turbine Co., Ltd

Hangzhou Steam Turbine Co., Ltd

Qingdao Jieneng Steam Turbine / MAN

SGS

Shandong Beichen

Hangzhou Boiler Group

Jiangsu Shuangliang Boiler Co., Ltd

Harbin Turbine Co., Ltd

Harbin Boilor Co., Ltd

Dongfang Boilor Co., Ltd

Jiangsu Livo New Energy

Power Generator

Harbin Electric Company

Wolong ELectric Group Co.,Ltd

Dongfang Electric Co., Ltd

Shanghai Electric Co., Ltd

Shandong Jinan Power Equipment  Factory

Solar Field and Central Receiver

Beijing Shouhang IHW Resource  Saving Co., Ltd

Zhejiang Supcon Solar Energy  Technology

Shanghai Electric BrightSource

SEPCO 3

Dongfang Boilor Co., Ltd

Harbin Turbine Co., Ltd

SGS Molten Salt Circulating Pump

Ruhrpumpen China

Suzhou Sulzer Pump

Flowserve Flow Control Suzhou

Aliaxis

Molten Salt Thermostat pump

Jiangsu Feiyue Machine and Pump  Group

Jiangsu Jinlin Chemical Machinery  Co., Ltd

Jinan Warwick Pump Co., Ltd

Suzhou Sulzer Pump

Beijing Power Equipment Group

Molten Salt Tank

Bluestar Beijing Chemical Machinery  Co., Ltd

Molten Salt Tank Electric Heater

Chromalox

DCS

Nanjing Sciyon Automation Group  Co., Ltd

Potassium Nitrate

Jiaocheng Bingsheng Chemical

Heat Tracing - Receiver System

Chromalox

Heat Tracing

Bartec

DCS Stimulator

State Nuclear Power Automation  System Engineering

                                                                                                                                                                            

 Plant photos






More from CSP Focus

Next

Latest News

See more+
  • Confirmed Speakers and Panelists of 11th CSP Focus China 2021

    We are pleased to announce 11th CSP Focus China 2021, which will be held on Oct. 28-29 in Beijing, China this year.The conference will be ON LINE too, with instant bilingual translation, given the constraints of international travel currently.Confirmed Speakers and Panelists:Ms. Jingli Shi, Researcher, Energy Research Institute, NDRCMr. Jixue Wang, Deputy Director of RE Center, EPPEIMr. Yanglong D

  • 247SOLAR CEO BRUCE ANDERSON TO INTRODUCE NEXT GENERATION LOW-COST CSP

    Great Falls, VA, USA Bruce Anderson, CEO of 247Solar Inc., will speak at the International CSP Focus 2021 Conference in Beijing, China on Friday, October 29, 2021. There he will present new modular, ultra-high temperature CSP technology that makes the unique round-the-clock benefits of CSP available at costs that rival daytime-only PV.For context: CSP has long offered unique benefits to the renewa

  • Qinghai 3*100MW CSP Bids Winner Announced - Coal and Oil Giants Grasp CSP

    Qinghai Province, China. 28 Sept, 2021. Qinghai Government announced the winners of a total capacity of 5.3GW RE auctions today, among which 3*100MW of CSP projects, 3.5GW PV and 1.5GW Wind, slightly different from the previous RFP document, in which there are 3*100MW of CSP projects, 3.8GW PV and 1.2GW Wind. Project Allocations3 companies and 4 consortia companies wins the bids, as was shown on t

  • Bids Open - 2*100MW CSP Included in Jilin China

    Jilin Province, China.Sept 23rd, four bidders (consortia) won the auction of a total capacity of 1.4GW RE projects, among which 2*100MW CSP Projects were included. The winners are State Power Investment Corporation (SPIC) & Zhejiang Zhongguang New Energy for Bid One, Power China for Bid Two, China General Nuclear Group (CGN) & Baicheng Energy Investment Development for Bid Three, and China

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news