CPECC Hami 50MW Tower CSP Project

<BACK

   2022-7


 Project Schedule



  ● 2019-3-2, Installation of SGS system equipments Started

  ● 2019-3-14Installation of Steam Turbine and Generator Completed

  ● 2019-5-8Installation of Receiver Started

  ● 2019-6-7Installation of Receiver Supporting Structure Completed

  ● 2019-9-21Two Hot Salt Pumps Installed

  ● 2019-10-5Installation of Receiver Plates Started

  ● 2019-10-16Three Cold Salt Pumps and Two Thermoregulation Pumps Installed

  ● 2019-11-18Salt Melting Started

  ● 2019-12-18Salt Melting Completed

  ● 2019-12-24Installation of Receiver Completed

  ● 2019-12-29Grid Connection

  ● 2021-6-18Grid Connection and Power Generation during the Night

  ● 2021-9-6Grid Connection with Full Capacity

  ● 2021-9-27240 Hours Continous Operation Test Passed


           Full report 

      (Membership Only) 


 Project Overview


Enlisted in China CSP Pilot Projects, CPECC Hami 50MW Tower CSP Project was located in Naomaohu Town, Yiwu County, Hami,Xinjiang.

 

With planned capacity 2*50MW, the phase one of 50MW will use molten salt tower technology, and the construction period was estimated to be 21 months.


Apply CSP Focus Membership to see full report


Project Participants

 

Apply CSP Focus Membership to see full report

                                                                                                                                                                            

 Plant photos






More from CSP Focus

Next

Latest News

See more+
  • Dubai’s concentrated solar power project starts supplying electricity to the grid

    On November 29 (Dubai Time), the Trough Unit No. 1 facility of Shanghai Electric’s 700MW solar thermal and 250MW photovoltaic solar power plant in Dubai has successfully achieved grid-connected electricity generation, marking a significant milestone along the path of the firm’s entry into the renewable energy sector. The facility is already delivering top-notch technical parameters and reliable

  • Four bidders shortlisted for 200MW solar plant

    The plant, which will use lenses or mirrors to focus a large area of sunlight onto a receiver, is due to be operational by 2027 and is the flagship renewable project in government’s Integrated Resources Plan (IRP) for energy development in the years to 2040.On Tuesday, the Ministry of Minerals and Energy published a shortlist of four bidders who include major global players with thousands of mega

  • CSP Project Tenders Last Week (Nov.14-20)

    Project Construction Supervision Bidding- POWERCHINA Ruoqiang 100MW CSP + 900MW PV ProjectOn Nov. 14, POWERCHINA Renewable Energy Co., Ltd issued a tender announcement for the construction supervision of the POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project. According to the announcement, the owner of POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project is POWERCHINA Ruoqiang Ruida Energy Development C

  • CSP Project Tenders Last Two Week (Nov. 1-13)

    Vacuum Pump Tender- Akesai Huidong New Energy CSP + PV Pilot ProjectOn November 7, East China Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group issued a procurement announcement for vacuum pumps for the Akesai Huidong New Energy CSP + PV Pilot Project.Latest Milestone- Akesai Huidong New Energy CSP + PV Pilot ProjectAccording to the Aksai County Government, the

Reports(Member Only)

See more+

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news