Yumen Xinneng 50MW molten salt tower CSP plant

<BACK

2019-8-13


Project Schedule

  


● Sept.30, 2019 (expected), Modules No.1-3 connected to the grid

● July, 2019, Module No.1 tested and molten salt was heated to 570℃; Heliostats of Module No.2 almost installed; Modules No.3-10 under construction

● March, 2019, steam turbine & steam generation equipment installed

● Aug.5th, 2018, main transformer installed

● April, 2018, foundation of steam turbine started construction; Modules No.2-5 started construction 

● March, 2018, overall installation of Module No.1 completed

● Dec.7, 2017, molten salt TES started constructio 

Dec. 4, 2017, heat exchanger bidders announced & steam generator bidding restarted.  

● September, 2017, designing plan reviewed

● Jun.8, 2017, officially broke ground

● Dec.16, 2016, feasibility study meeting held


     Full report view online


Project Overview


Yumen Xinneng 50MW molten salt tower CSP plant was officially selected as one of China 1st batch of CSP pilot projects in September 2016. With total investment of RMB 1.78 billion, the project is expected to be completed in 2 years. The project is located in Zhengjiashawo CSP Park, 15km far from new downtown of Yumen city, Gansu Province. The 50MW project takes beam-down CSP technology with 15 mirror field modules, and one 9-hour molten salt thermal storage system & steam turbine set. The annual generating capacity is under load of 4328 hours. 


The project broke ground in June 2017, and 3 of the 15 modules are expected to be connected to the gird by the end of September, 2019. It will be the first large-scale commercial CSP plant in the world taking innovative beam-down molten salt tower CSP technology. 


As recognized by CSP industry players, the Direct Normal Irradiance (DNI) should be above 1,700kW.h/㎡, and the DNI in Yumen is around 1,901 kW.h/㎡, indicating that Yumen is rich in solar resources and a great place for building CSP plants.

     

Basic information

Location

Zhengjiashawo CSP Park

Capacity

50MW

Investment

1.78 billion

Annual generating capacity

4328h

Thermal energy stroage hours

9h


Project Participants


Tendering Item

Bidding Winner

Turnkey EPC

CSEEC-China Sinogy  Electric Engineering Co.,Ltd.

Subcontractor of Energy Collecting  and Storage System (Equipments such as Heliostats, Beam-down Tower, Central  Receiver, Molten Salt Tank…and construction)

Jiangsu Xinchen CSP

Turnkey EPC of Central Storage  Tank

China Chengda  Engineering Co., Ltd.

Thermal Insulation for TES  Tank/Heat Receiver/Pipeline

LUYANG ENERGY-SAVING  MATERIALS CO.,LTD.

Molten Salt Vertical Pump

Ruhrpumpen

Electric Heat Tracing

MICC

Steam Turbine

Shanghai Turbine  Works Co., Ltd.

Electric Generator

JPEF-SHANDONG JINAN  POWER EQUIPMENT FACTORY

Low Voltage Cabinet

Schneider Electric

Steam Generator

Dongfang Boiler  Group Co., Ltd

Air Cooling/Dry Cooling System

SEC - SPX  Engineering Technology Co., Ltd.

Molten Salt Storage Tank Heater

Zoppas Industries

Stainless Material for TES Tank  Manufacture

Taiyuan  Iron&Steel (Group) Co.,Ltd

Ultrasonic Flowmeter

Flexim

Molten Salt Ultrasonic Flowmeter

Krohne

Fastener

EPRESS SYSTEMS  (SHENZHEN) LTD

300t Molten Salt-Sodium Nitrate

Hualong Ammonium  Nitrate Co.,Ltd Shandong Ocean Chemical

Power Block Construction &  Installation

JEPC3-China Energy  Engineering Group Jiangsu No.3 Electric Power Construction Co., Ltd.

                                                                                          

 Plant photos


More from CSP Focus

Next

Latest News

See more+
  • Azelio Sets up Concentrated Solar Power Project in Zambia

    Azelio has signed a Memorandum of Understanding (MoU) with the Swedish company Nordic Distributed Power AB(ND Power) for a small-scale project in Zambia.The installation will operate under real-world commercial terms and serve as a model for ND Power’s future installations in the Southern African region.The initial project is a plant of 50 kWe in Zambia,set to become operational in Q3 2020. Azeli

  • Egypt plans to establish $1.2bn CSP solar power plants

    Smart Engineering Solutions, in cooperation with the Ministry of Military Production, plans to launch concentrated solar power (CSP) plants and manufacture components of this system in Egypt with investments of $ 1.2bn. Osama Kamal, companys chairpersontold Daily News Egypt that they started the selection process of CSP companies to cooperate with, “from a shortlist of up to16 companies, by the e

  • Morocco extends deadline for Noor Midelt II bids; Lebanon launches feasibility study for first CSP plant

    Morocco extends tender deadline for 230 MW Noor Midelt II projectThe Moroccan Sustainable Energy Agency (Masen) has extended the tender deadline for the 230 MW Noor Midelt II CSP-PV project by a "few additional weeks" to later this month, Moroccan media reported October 9.The Noor Midelt II tender was launched in July and developers originally had until September 16 to submit their proje

  • Cerro Dominador CSP developer plans larger plants in Chile

    The ground-breaking 110 MW Cerro Dominador CSP plant could start commissioning by end of 2019 and the fund-owned developer is studying larger projects at three other sites in northern Chile, Francisco Vizcaino, Project Director at Cerro Dominador, told New Energy Update.Successful completion of the Cerro Dominador project in Chile will boostinvestor confidence in CSP and support further projects i

Free Reports

See more+
  • BrightSource Engineering and Manufacturing System

    Engineering, Supply Chain, Construction, Business Intelligence. What about the Min O&M?

  • Yumen Xinneng 50MW Molten Salt Tower CSP Project

    The project broke ground in June 2017, and 3 of the 15 modules are expected to be connected to the gird by the end of September, 2019. It will be the first large‐scale commercial CSP plant in the world taking innovative beam-down molten salt tower CSP technology.

  • Luneng Haixi 50MW Molten Salt Tower CSP Project

    With total capacity of700MW, Luneng Haixi Geermu Multi-energy Complement Integration OptimizationPilot Project consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energystorage system. Updating--Jan., 2019 Edition1. Overview (P2)2. Highlights (P2)3. Fast sheet (P3)4. Project Milestones (P4)5. Project Participants 5.1. Developer (P5) 5.2. Owner&Investor (P5) 5.3. EPC Contractor (P5)

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

Upcoming Events

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news