Yumen Xinneng 50MW molten salt tower CSP plant

<BACK

2020-1-14


Project Schedule

  


● Before the middle of 2020 (expected), Modules No.1-3 connected to the grid

● July, 2019, Module No.1 tested and molten salt was heated to 570℃; Heliostats of Module No.2 almost installed; Modules No.3-10 under construction

● March, 2019, steam turbine & steam generation equipment installed

● Aug.5th, 2018, main transformer installed

● April, 2018, foundation of steam turbine started construction; Modules No.2-5 started construction 

● March, 2018, overall installation of Module No.1 completed

● Dec.7, 2017, molten salt TES started constructio 

Dec. 4, 2017, heat exchanger bidders announced & steam generator bidding restarted.  

● September, 2017, designing plan reviewed

● Jun.8, 2017, officially broke ground

● Dec.16, 2016, feasibility study meeting held


     Full report view online


Project Overview


Yumen Xinneng 50MW molten salt tower CSP plant was officially selected as one of China 1st batch of CSP pilot projects in September 2016. With total investment of RMB 1.78 billion, the project is expected to be completed in 2 years. The project is located in Zhengjiashawo CSP Park, 15km far from new downtown of Yumen city, Gansu Province. The 50MW project takes beam-down CSP technology with 15 mirror field modules, and one 9-hour molten salt thermal storage system & steam turbine set. The annual generating capacity is under load of 4328 hours. 


The project broke ground in June 2017, and 3 of the 15 modules are expected to be connected to the gird by the end of September, 2019. It will be the first large-scale commercial CSP plant in the world taking innovative beam-down molten salt tower CSP technology. 


As recognized by CSP industry players, the Direct Normal Irradiance (DNI) should be above 1,700kW.h/㎡, and the DNI in Yumen is around 1,901 kW.h/㎡, indicating that Yumen is rich in solar resources and a great place for building CSP plants.

     

Basic information

Location

Zhengjiashawo CSP Park

Capacity

50MW

Investment

1.78 billion

Annual generating capacity

4328h

Thermal energy stroage hours

9h


Project Participants


Tendering Item

Bidding Winner

Turnkey EPC

CSEEC-China Sinogy  Electric Engineering Co.,Ltd.

Subcontractor of Energy Collecting  and Storage System (Equipments such as Heliostats, Beam-down Tower, Central  Receiver, Molten Salt Tank…and construction)

Jiangsu Xinchen CSP

Turnkey EPC of Central Storage  Tank

China Chengda  Engineering Co., Ltd.

Thermal Insulation for TES  Tank/Heat Receiver/Pipeline

LUYANG ENERGY-SAVING  MATERIALS CO.,LTD.

Molten Salt Vertical Pump

Ruhrpumpen

Electric Heat Tracing

MICC

Steam Turbine

Shanghai Turbine  Works Co., Ltd.

Electric Generator

JPEF-SHANDONG JINAN  POWER EQUIPMENT FACTORY

Low Voltage Cabinet

Schneider Electric

Steam Generator

Dongfang Boiler  Group Co., Ltd

Air Cooling/Dry Cooling System

SEC - SPX  Engineering Technology Co., Ltd.

Molten Salt Storage Tank Heater

Zoppas Industries

Stainless Material for TES Tank  Manufacture

Taiyuan  Iron&Steel (Group) Co.,Ltd

Ultrasonic Flowmeter

Flexim

Molten Salt Ultrasonic Flowmeter

Krohne

Fastener

EPRESS SYSTEMS  (SHENZHEN) LTD

300t Molten Salt-Sodium Nitrate

Hualong Ammonium  Nitrate Co.,Ltd Shandong Ocean Chemical

Power Block Construction &  Installation

JEPC3-China Energy  Engineering Group Jiangsu No.3 Electric Power Construction Co., Ltd.

                                                                                          

 Plant photos


More from CSP Focus

Next

Latest News

See more+
  • Making Solar Hydrogen with a Side of Carbon Nanotubes

    IMAGE@Hiroyuki Kimura, IHI Corporation Heat & Fluid Dynamics Research DepartmentTwo teams of solar researchers have developed a novel solar reactor and thermochemical process for making solar hydrogen that can generate in addition carbon black and graphite as well as carbon nanotubes. Working over a six-year period, the teams first developed the specific solar reactor, and then subsequently,

  • Solar Energy Center developed LCOE Map for installation of CSP plants in Chile

    Among other results, the study carried out by researchers at the Center for Solar Energy Technologies of Fraunhofer Chile, shows that the optimal location to install a CSP tower plant, due to costs and solar potential, is near the city. de Copiapó, with a LCOE -level energy cost- of 77 USD / MWh and with a plant factor of close to 80%.Achieving decarbonization goals at the national level, eff

  • FROM GREEN DEAL TO GREEN RECOVERY: A joint initiative of the EU solar industry

    View Full Statement in PDFIn early 2020, the proposal of the European Commission to launch a “Green Deal” set an ambitious double objective for the sake of European citizens’ wealth and health : increasing the European contribution to fight climate change while boosting the European economy.Within a few months, the COVID-19 crisis added a dramatic level of urgency to act – beyond single natio

  • The Concentrated Solar Thermal Industry supports the Green Recovery Plan through a truly smart sector integration

    ESTELA welcomes and supports the endeavour of the European Commission bringing together the Green Deal and the Recovery Plan. This initiative of the Commission constitutes a strong action framework impacting the depth and pace of the decarbonisation of the electricity, industry, and transport sectors. The European Solar Industry is ready to support it towards the deployment of innovative multi-tec

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)