CSNP Royal Tech Urat 100MW Parabolic Trough CSP Project

<BACK

   2022-7


Project Schedule


  • 2016-5-19,commencement of project feasibility study evaluation meeting

  • 2016-10,project approval by Bayannur City

  • 2016-11-14,evaluation closure of project feasibility study

  • 2017-4-28,Groundbreaking ceremony

  • 2017-7-21,site leveling started

  • 2017-7-29,China Shipbuilding New Power Co., Ltd won EPC bidding

  • 2017-12,1st batch of 1365 high temperature vacuum receiver tubes sent to the plant site

  • 2018-4-11,basic engineering almost finished; 80% completion of site leveling

  • 2019-12-30,Trial Operation of Solar Field

  • 2020-1-8,Grid Connection

  • 2020-11-5,Commissioning

  • 2020-12-16,Operation in Full Capacity

  • 2021-6-6,Salt Melting Completed and Commissioning of TES System

  • 2021-10-29,Demonstration Project Acceptance


Full report (Member Only)


Project Overview


As one of the first batch of 20 pilot CSP projects, CSNP Royal Tech Urat 100MW Parabolic Trough CSP Project is the largest trough plant within the pilot projects, in terms of installed capacity.

 

Located in Hailiutu Town, Urat Zhongqi,Bayannur City, Inner Mongolia, with the total investment of around RMB2.9 billion, the project takes an area of 5,000,000 m², equipped with 375 PT loops and 10 hours' TES system.


Apply CSP Focus Membership to see full report

                                                                 

Project Participants

 

Apply CSP Focus Membership to see full report

                                                                                                                                                                                                                               

 Plant photos



Latest News

See more+
  • Dubai’s concentrated solar power project starts supplying electricity to the grid

    On November 29 (Dubai Time), the Trough Unit No. 1 facility of Shanghai Electric’s 700MW solar thermal and 250MW photovoltaic solar power plant in Dubai has successfully achieved grid-connected electricity generation, marking a significant milestone along the path of the firm’s entry into the renewable energy sector. The facility is already delivering top-notch technical parameters and reliable

  • Four bidders shortlisted for 200MW solar plant

    The plant, which will use lenses or mirrors to focus a large area of sunlight onto a receiver, is due to be operational by 2027 and is the flagship renewable project in government’s Integrated Resources Plan (IRP) for energy development in the years to 2040.On Tuesday, the Ministry of Minerals and Energy published a shortlist of four bidders who include major global players with thousands of mega

  • CSP Project Tenders Last Week (Nov.14-20)

    Project Construction Supervision Bidding- POWERCHINA Ruoqiang 100MW CSP + 900MW PV ProjectOn Nov. 14, POWERCHINA Renewable Energy Co., Ltd issued a tender announcement for the construction supervision of the POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project. According to the announcement, the owner of POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project is POWERCHINA Ruoqiang Ruida Energy Development C

  • CSP Project Tenders Last Two Week (Nov. 1-13)

    Vacuum Pump Tender- Akesai Huidong New Energy CSP + PV Pilot ProjectOn November 7, East China Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group issued a procurement announcement for vacuum pumps for the Akesai Huidong New Energy CSP + PV Pilot Project.Latest Milestone- Akesai Huidong New Energy CSP + PV Pilot ProjectAccording to the Aksai County Government, the

Reports(Member Only)

See more+

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news