This page provides information on TSE1, a concentrating solar power (CSP) project, with data organized by background, participants, and power plant configuration. TSE1 is the first commercial solar thermal power plant based on direct steam generation.

                                  

Project Overview
Project Name:Thai Solar Energy 1 (TSE1)
Country:Thailand
Location:Huai Kachao (Kanchanaburi Province)
Owner(s):Thai Solar Energy Co.Ltd. (100%)
Technology:Parabolic trough
Turbine Capacity:Net: 5.0 MW Gross: 5.0 MW
Status:Operational
Start Year:2012

                                                                                                                                                                                    

Background
Technology:Parabolic trough
Status:Operational
Country:Thailand
City:Huai Kachao
Region:Kanchanaburi Province
Lat/Long Location:14°20′ 1.0″ North, 99°42′ 33.0″ East
Land Area:110 hectares
Electricity Generation:8,000 MWh/yr (Expected)
Start Production:2012/1/25
Construction Job-Years:120
Annual O&M Jobs:10
PPA/Tariff Type:Feed-in Tariff
PPA/Tariff Rate:11.5 Baht/kWh
PPA/Tariff Period:10 years
Project Type:Commercial
Participants
Developer(s):Solarlite GmbH
Owner(s) (%):Thai Solar Energy Co.Ltd. (100%)
EPC Contractor:Solarlite GmbH
Operator(s):Thai Solar Energy Co.Ltd.
Generation Offtaker(s):Electricity Generating Authority of Thailand
SCA Manufacturer (Model):Solarlite GmbH (SL 4600)
Mirror Manufacturer:Guardian & AGC
HCE Manufacturer:Schott
Turbine Manufacturer:MAN (MARC 2)
Solar Field
Solar-Field Aperture Area:45,000 m²
# of Solar Collector  Assemblies (SCAs):86
# of Loops:19
SCA Length:120 m
# of Modules per SCA:10
Heat-Transfer Fluid Type:Water/Steam
Solar-Field Inlet Temp:201°C
Solar-Field Outlet Temp:340°C
Power Block
Turbine Capacity (Gross):5.0 MW
Turbine Capacity (Net):5.0 MW
Power Cycle Pressure:30.0 bar
Cooling Method:Wet cooling
Cooling Method Description:Cooling tower (evaporation cooling)
Annual Solar-to-Electricity  Efficiency (Gross):12%
Fossil Backup Type:None
Thermal Storage
Storage Type:None


*Reference from NREL

More from CSP Focus

Next

Latest News

See more+

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news