Project Overview
Project Name:ACME Solar Tower
Country:India
Location:Bikaner (Rajasthan)
Owner(s):ACME Group (100%)
Technology:Power tower
Turbine Capacity:Net: 2.5 MW Gross: 2.5 MW
Status:Operational
Start Year:2011

                                                                                                                                    

Background
Technology:Power tower
Status:Operational
Country:India
City:Bikaner
Region:Rajasthan
Lat/Long Location:28°11′ 2.0″ North, 73°14′ 26.0″ East
Land Area:12 acres
Start Production:2011/4/1
Participants
Developer(s):ACME Group ; eSolar
Owner(s) (%):ACME Group (100%)
Operator(s):ACME Group
Heliostat Manufacturer:eSolar
Receiver Manufacturer:Victory Energy
Turbine Manufacturer:MaxWatt
Solar Field
Heliostat Solar-Field  Aperture Area:16,222 m²
# of Heliostats:14,280
Heliostat Aperture Area:1.136 m²
Tower Height:46 m
Heat-Transfer Fluid Type:Water/Steam
Receiver Inlet Temp:218C
Receiver Outlet Temp:440C
Power Block
Turbine Capacity (Gross):2.5 MW
Turbine Capacity (Net):2.5 MW
Output Type:Steam Rankine
Power Cycle Pressure:60.0 bar
Cooling Method:Wet cooling
Cooling Method Description:Cooling Towers
Thermal Storage
Storage Type:None


*Reference from NREL

More from CSP Focus

Next

Latest News

See more+
  • Dubai’s concentrated solar power project starts supplying electricity to the grid

    On November 29 (Dubai Time), the Trough Unit No. 1 facility of Shanghai Electric’s 700MW solar thermal and 250MW photovoltaic solar power plant in Dubai has successfully achieved grid-connected electricity generation, marking a significant milestone along the path of the firm’s entry into the renewable energy sector. The facility is already delivering top-notch technical parameters and reliable

  • Four bidders shortlisted for 200MW solar plant

    The plant, which will use lenses or mirrors to focus a large area of sunlight onto a receiver, is due to be operational by 2027 and is the flagship renewable project in government’s Integrated Resources Plan (IRP) for energy development in the years to 2040.On Tuesday, the Ministry of Minerals and Energy published a shortlist of four bidders who include major global players with thousands of mega

  • CSP Project Tenders Last Week (Nov.14-20)

    Project Construction Supervision Bidding- POWERCHINA Ruoqiang 100MW CSP + 900MW PV ProjectOn Nov. 14, POWERCHINA Renewable Energy Co., Ltd issued a tender announcement for the construction supervision of the POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project. According to the announcement, the owner of POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project is POWERCHINA Ruoqiang Ruida Energy Development C

  • CSP Project Tenders Last Two Week (Nov. 1-13)

    Vacuum Pump Tender- Akesai Huidong New Energy CSP + PV Pilot ProjectOn November 7, East China Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group issued a procurement announcement for vacuum pumps for the Akesai Huidong New Energy CSP + PV Pilot Project.Latest Milestone- Akesai Huidong New Energy CSP + PV Pilot ProjectAccording to the Aksai County Government, the

Reports(Member Only)

See more+

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news