Phase Four of Mohammed bin Rashid Al Maktoum Solar Park 30% complete says DEWA

2019.09.25     From: me construction news

Construction of Phase Four of the Mohammed bin Rashid Al Maktoum Solar Park is progressing at pace and stands at over 30% complete. Once ready, the fourth phase will generate 950 megawatts (MW) at an investment of $4.29bn.

Phase Four boasts Concentrated Solar Power (CSP) and photovoltaic technology. According to a statement from DEWA, this phase has the capacity to provide clean energy for 320,000 residences and will help reduce 1.6m tonnes of carbon emissions annually.

The scope of work on this phase of the project includes the construction of the world’s tallest 260m solar tower and the world’s largest global thermal storage capacity of 15 hours; allowing for energy availability round-the-clock, DEWA said.

Phase Four will leverage three technologies to produce 950MW of clean energy, said Saeed Mohammed Al Tayer, MD & CEO of DEWA, while on an inspection visit to the site. He was accompanied by Waleed Salman, executive VP of Business Development and Excellence at DEWA and Jamal Shaheen Al Hammadi, VP of Clean Energy & Diversification, and a number of DEWA officials.

Al Tayer said the project will feature 700MW of CSP, 600MW from a parabolic basin complex and 100MW from a solar tower and 250MW from photovoltaic solar panels.

During the visit, Abdul Hamid Al Muhaidib, the executive managing director of Noor Energy 1, briefed Al Tayer on construction progress. Noor Energy 1 is a JV between DEWA, Saudi Arabia’s Acwa Power, and China’s Silk Road Fund.

Discussing project progress, Al Muhaidib said more than 30% of the work on Phase Four has been completed, with the central solar tower climbing beyond 50m. The foundation of molten salt tanks and turbines has also been finished, he stated. The parabolic trough (PT) production line was recently inaugurated to produce the first of 63,600 units, the statement said.

The overall progress of the Mohammed bin Rashid Al Maktoum Solar Park had reached 16%. Scheduled for fully completion in 2030, it will boast 5,000MW of clean energy generation capacity.





Upcoming CSP events:


3rd CSP Focus Innovation 2019(Oct.24-25, Beijing China)

10th CSP Focus China 2020 (March, Beijing China) 


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.


Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news