Luneng Haixi 50MW Molten Salt Tower CSP Project

<BACK

   2022-7


Project Schedule

 ● 2016-12-26, Project approval from National Energy Administration

 ● 2017-6-30, Project construction started

 ● 2018-3-20, Construction of Receiver Tower Foundation Started

 ● 2018-10, COD of PV and Wind projects

 ● 2018-11-21, Construction completion of receiver tower (147.4m of 181.1m)

 ● 2019-1-2, Civil work completed, equipment installation started

 ● 2019-2-28, Installation of Receiver Supporting Sturcture Started

 ● 2019-4-30, 2,100 heliostats installed (4,400 in total)

 ● 2019-6-6, Installation of Receiver Supporting Sturcture Completed

 ● 2019-7-4, Steam turbine and generator installed

 ● 2019-8-15, Salt Melting Started

 ● 2019-9-5, Grid connection acceptance

 ● 2019-9-19, Grid Connected Successfully

 ● 2020-8-27, 120 Hour Reliability Operation Passed


Full report (Member Only)


Project Overview


With total capacity of 700MW, Luneng Haixi Geermu Multi-energy Complement Integration Optimization Pilot Project consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energy storage system. 


The annual electricity generation is expected to be around 1262.5GWh after completion of the project, reducing standard coal consumption of 401,500 metric ton and dust emission of 5431.96 metric ton. The CSP plant is normally named Luneng Haixi 50MW Molten Salt Tower CSP Project, consisting of one 188m receiver tower, 4,400 heliostats, 12h thermal electricity storage system. 


The CSP project is expected to be operational before August 30th, 2019.


Apply CSP Focus Membership to see full report


Project Participants

   

Apply CSP Focus Membership to see full report

                                                                                                                                                              

 Plant photos






Latest News

See more+
  • Magtel launches a hybrid solar power plant that will produce energy at night in Hornachuelos

    The Cordoba-based engineering company Magtel has started the environmental consultation phase of the first hybrid renewable power plant to be proposed in the province of Cordoba. It will have (if it gets the papers) the two available solar technologies, solar thermal and photovoltaic, but it will have a peculiarity. You can create electrical energy at will. When the energy network demands it. Even

  • CSP Project Tenders Last Week (Sept 1-11)

    Equipment Procurement Tenders- CGN New Energy Jilin 100MW CSP ProjectOn September 2, Daan Guangtou Zhongneng CSP Company issued a bidding announcement for the turbine generator set, steam generation system, solar concentration and heat collection system, cold salt pump, hot salt pump and thermoregulation pump of CGN New Energy Jilin 100MW CSP Project.Tender for Turbine Systems-Tibet Mining Zabuye

  • Letlhakane Concentrated Solar Power Plant in Botswana

    The Letlhakane Concentrated Solar Power Plant is a planned 100 MWconcentrated solar power station in Botswana. The owner, developer and operator of this solar power complex will be an independent power producer, whose identity will be revealed when the ongoing open bidding is concluded. Bids were received until June 2022.The power generated here is expected to be bought by Botswana Power Corporati

  • DEWA receives four bids from international companies for sixth phase of solar park

    Dubai Electricity and Water Authority (DEWA) has received 4 bids from international companies for consultancy contract for the sixth phase of the Mohammed bin Rashid Al Maktoum Solar Park, Dubai Media Office (DMO) announced on Tuesday.The single-site solar park is the largest of its kind in the world, using the Independent Power Producer (IPP) model, with a production capacity of 5,000 megawatts b

Reports(Member Only)

See more+

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news