Power China Gonghe 50MW Molten Salt Tower CSP Project

<BACK

   2022-7


Project Schedule


  • 2015-8,Pre-Feasibility Study Completed

  • 2015-9,Project Company Registered

  • 2015-10-28,Project Registerd

  • 2015-11,Pilot Project Application

  • 2016-9-23,Selected as Pilot Project

  • 2016-11-29,Feasibility Study Evaluation and Inspection Meeting held in Beijing

  • 2017-6-18,Groundbreaking

  • 2018-3-6,Project Construction Started

  • 2018-4,Foundation of Receiver Tower Completed

  • 2018-6-28,On-site Installation of First Heliostat Completed

  • 2018-9-18,Receiver Tower Sealed Atop

  • 2018-11-22,Receiver Tower Concreting Completed

  • 2018-12-1,Generator Stator Installed

  • 2019-1-11,First Receiver Plate Installed

  • 2019-1-14,Heliostat Manufacturing Completed

  • 2019-5-13,Installation of Salt Tank Completed

  • 2019-5-15,Installation of Steam Turbine Completed

  • 2019-9-10,Grid Connection Acceptance

  • 2019-9-18,Steam Turbine Roll-up

  • 2019-9-19,Grid Connection

  • 2020-11-6,Operation in Full Capacity

  • 2020-11-28,240 Hour Continous Operation Test Passed

  • 2021-4-22,Demonstration Project Acceptance

Full report (Member Only)


Project Overview


Locatedin Hainan Eco Solar Energy Park, 12km southwest to Gonghe County of Qinghai Province, Power China Gonghe 50MW Molten Salt Tower CSP Project is selected as one of the first batch of pilot CSP projects in China. With strong support and commitment from the group company - Power China, the projectis under progress and supposed to be commissioned in mid 2019.


Apply CSP Focus Membership to see full report


Project Participants

Apply CSP Focus Membership to see full report

                                                                                                          

 Plant photos



Latest News

See more+
  • 2022 Annual Power Generation Exceeding the Design Value -- SUPCON SOLAR Delingha 50MW Molten Salt Tower CSP Plant Sees Another Good Year

    The total annual cumulative actual power generation of the SUPCON SOLAR Delingha 50MW Molten Salt Tower CSP Plant in 2022 was 146.4 GWh, i.e. 100.26% of the designed annual power generation (146GWh), completing yearly target.The plant has been operating in good conditions. As shown in the monthly power generation in Figure 1, it has 124 days seeing a completion of 100% of the designed generation.

  • Dubai’s concentrated solar power project starts supplying electricity to the grid

    On November 29 (Dubai Time), the Trough Unit No. 1 facility of Shanghai Electric’s 700MW solar thermal and 250MW photovoltaic solar power plant in Dubai has successfully achieved grid-connected electricity generation, marking a significant milestone along the path of the firm’s entry into the renewable energy sector. The facility is already delivering top-notch technical parameters and reliable

  • Four bidders shortlisted for 200MW solar plant

    The plant, which will use lenses or mirrors to focus a large area of sunlight onto a receiver, is due to be operational by 2027 and is the flagship renewable project in government’s Integrated Resources Plan (IRP) for energy development in the years to 2040.On Tuesday, the Ministry of Minerals and Energy published a shortlist of four bidders who include major global players with thousands of mega

  • CSP Project Tenders Last Week (Nov.14-20)

    Project Construction Supervision Bidding- POWERCHINA Ruoqiang 100MW CSP + 900MW PV ProjectOn Nov. 14, POWERCHINA Renewable Energy Co., Ltd issued a tender announcement for the construction supervision of the POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project. According to the announcement, the owner of POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project is POWERCHINA Ruoqiang Ruida Energy Development C

Reports(Member Only)

See more+

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news