Power China Gonghe 50MW Molten Salt Tower CSP Project

<BACK

   2022-7


Project Schedule


  • 2015-8,Pre-Feasibility Study Completed

  • 2015-9,Project Company Registered

  • 2015-10-28,Project Registerd

  • 2015-11,Pilot Project Application

  • 2016-9-23,Selected as Pilot Project

  • 2016-11-29,Feasibility Study Evaluation and Inspection Meeting held in Beijing

  • 2017-6-18,Groundbreaking

  • 2018-3-6,Project Construction Started

  • 2018-4,Foundation of Receiver Tower Completed

  • 2018-6-28,On-site Installation of First Heliostat Completed

  • 2018-9-18,Receiver Tower Sealed Atop

  • 2018-11-22,Receiver Tower Concreting Completed

  • 2018-12-1,Generator Stator Installed

  • 2019-1-11,First Receiver Plate Installed

  • 2019-1-14,Heliostat Manufacturing Completed

  • 2019-5-13,Installation of Salt Tank Completed

  • 2019-5-15,Installation of Steam Turbine Completed

  • 2019-9-10,Grid Connection Acceptance

  • 2019-9-18,Steam Turbine Roll-up

  • 2019-9-19,Grid Connection

  • 2020-11-6,Operation in Full Capacity

  • 2020-11-28,240 Hour Continous Operation Test Passed

  • 2021-4-22,Demonstration Project Acceptance

Full report (Member Only)


Project Overview


Locatedin Hainan Eco Solar Energy Park, 12km southwest to Gonghe County of Qinghai Province, Power China Gonghe 50MW Molten Salt Tower CSP Project is selected as one of the first batch of pilot CSP projects in China. With strong support and commitment from the group company - Power China, the projectis under progress and supposed to be commissioned in mid 2019.


Apply CSP Focus Membership to see full report


Project Participants

Apply CSP Focus Membership to see full report

                                                                                                          

 Plant photos



Latest News

See more+
  • Magtel launches a hybrid solar power plant that will produce energy at night in Hornachuelos

    The Cordoba-based engineering company Magtel has started the environmental consultation phase of the first hybrid renewable power plant to be proposed in the province of Cordoba. It will have (if it gets the papers) the two available solar technologies, solar thermal and photovoltaic, but it will have a peculiarity. You can create electrical energy at will. When the energy network demands it. Even

  • CSP Project Tenders Last Week (Sept 1-11)

    Equipment Procurement Tenders- CGN New Energy Jilin 100MW CSP ProjectOn September 2, Daan Guangtou Zhongneng CSP Company issued a bidding announcement for the turbine generator set, steam generation system, solar concentration and heat collection system, cold salt pump, hot salt pump and thermoregulation pump of CGN New Energy Jilin 100MW CSP Project.Tender for Turbine Systems-Tibet Mining Zabuye

  • Letlhakane Concentrated Solar Power Plant in Botswana

    The Letlhakane Concentrated Solar Power Plant is a planned 100 MWconcentrated solar power station in Botswana. The owner, developer and operator of this solar power complex will be an independent power producer, whose identity will be revealed when the ongoing open bidding is concluded. Bids were received until June 2022.The power generated here is expected to be bought by Botswana Power Corporati

  • DEWA receives four bids from international companies for sixth phase of solar park

    Dubai Electricity and Water Authority (DEWA) has received 4 bids from international companies for consultancy contract for the sixth phase of the Mohammed bin Rashid Al Maktoum Solar Park, Dubai Media Office (DMO) announced on Tuesday.The single-site solar park is the largest of its kind in the world, using the Independent Power Producer (IPP) model, with a production capacity of 5,000 megawatts b

Reports(Member Only)

See more+

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news