Power China Gonghe 50MW Molten Salt Tower CSP Project

<BACK

   2019-1-31


Project Schedule


  January 14th2019, heliostat completed  New! 

 ● December 1st, 2018, Generator Stator Installed

 ● November 22nd, 2018, Receiver Tower Concreting Completed

 ● September 18th, 2018, Receiver Tower Sealed Atop

 ● June 28th, 2018, On-site Installation of First Heliostat Completed

 ● June 18th, 2018, Project Construction Started

 ● April, 2018, Foundation of Receiver Tower Completed

 ● November 29th, 2016, Feasibility Study Evaluation and Inspection Meeting

 ● September 23rd, 2016, Selected as Pilot Project

 ● November, 2015, Pilot Project Application

 ● October 28th, 2015, project registerd      

 ● September, 2015, Project Company Registered

 ● August,2015, Pre-Feasibility Study Completed

Full report view online


Project Overview


Locatedin Hainan Eco Solar Energy Park, 12km southwest to Gonghe County of Qinghai Province, Power China Gonghe 50MW Molten Salt Tower CSP Project is selected as one of the first batch of pilot CSP projects in China. With strong support and commitment from the group company - Power China, the projectis under progress and supposed to be commissioned in mid 2019.


Basic Information

Location

Gonghe, Hainan Area, Qinghai Province

Longitude and  Latitude

N36°6′8″E100°37′30″

DNI

~1900kWh//year

Installed Capacity

50MW

Technology

Molten Salt Tower CSP

Storage

6 Hours

Starting Date

2017-6-18

Status

Under Construction

COD

2019 (expected)

Annual Electricity  Generation

156.92GWh (expected)

Annual Operation  Time

3,138 Hours

Total Investment

RMB 1.222 Billion

                                                                 

Project Participants

                                                                                                                

Equipment

Bidders

                                    (Winners are  highlighted)

Solar Field and Receiver
Highest: over RMB 900 Million
Lowest: around RMB 500 Million
Average: around 650 Million

Shanghai  Electric BrightSource Solar Energy Co., Ltd

Beijing Shouhang  IHW Resource Saving Technology Co., Ltd

Beijing Babcock  & Wilcox / Thermal Focus

Zhejiang Supcon  Solar Energy Technology Co., Ltd

Harbin Turbine  Co., Ltd

Power China  Nuclear Engineering Co., Ltd

Molten Salt
Average: Around RMB 52 Million

Qinghai Enesoon  New Material Technology Co., Ltd

Shanghai Salt  Lake Wentong Chemical Co., Ltd

SNM

Jiaocheng  Bingsheng Chemical Co., Ltd

Qinghai Lianda  Chemical Co., Ltd

SGS

Shanghai Boiler  Works, Ltd.

Steam Turbine

Harbin Turbine  Co., Ltd

Air Cooling System

Beijing Shouhang  IHW Resource Saving Technology Co., Ltd

Cold Molten Salt Pump

Flowserve/DIVERSE  ELECTRONICS

Hot Molten Salt Pump

Flowserve/DIVERSE  ELECTRONICS

Salt Drain Pump&Auxiliary Electrical  Equipment

Jiangsu Jinlin  Chemical Machinery Co., Ltd.

Regulating Valve

Flowserve/DIVERSE  ELECTRONICS

Molten Salt Triple Eccentric Butterfly  Valve

Beijing Zhonghui  Datong / OHL

Molten Salt Tank

Power China  Nuclear Engineering Co., Ltd / Power China

Hubei Electric Engineering Co.,  Ltd

Receiver

Hangzhou Boiler  Group

HTF&TES Installation and  Commissioning

Power China  SEPCO1 Electric Power Construction Co., Ltd

Reflecting Mirror

Daming Glass

Linear Motion Actuator

Wuxi HongBa  Mechanical Electrical Equipment Co.,Ltd.

Electric Heater - Molten Salt Tank

Chromalox/Thermal  Focus

Heat Tracing

MICC

Heat Tracing - Molten Salt Piping

Jiusheng  Electric Co., Ltd

DCS

Zhejiang Supcon  Solar Energy Technology Co., Ltd

                                                                                                                                                                                                                              

 Plant photos



Latest News

See more+
  • Construction progress on MBR Solar Park – Phase 4's 260m solar tower

    PICTURES: The development of Phase 4s solar tower is 7% ahead of schedule, whilst its solar field is 73% completeHE Saeed Mohammed Al Tayer, managing director and chief executive officer of Dubai Electricity and Water Authority (Dewa), has received a construction update on Phase 4 of the Mohammed bin Rashid Al Maktoum Solar Park (MBR Solar Park) project, including its 260m-tall solar tower, in Dub

  • MD & CEO reviews construction of 4th phase of the Mohammed bin Rashid Al Maktoum Solar Park

    HE Saeed Mohammed Al Tayer, MD & CEO of Dubai Electricity and Water Authority (DEWA), has inspected the 4th phase of the Mohammed bin Rashid Al Maktoum Solar Park. The 4th phase is the largest single-site Concentrated Solar Power (CSP) project in the world. Based on the Independent Power Producer (IPP) model, it will generate 950 megawatts (MW) at an investment of AED 15.78 billion.During the

  • MISP strengthening UAE’s solar power capacities with novel CSP and TES technologies

    Concentrating Solar Power (CSP) systems are considered a promising solar power technology for large-scale power generation. When CSP is coupled with thermal energy storage (TES), it is capable of producing constant power (base load) for up to 24 hours a day, making it well suited for integration to the electric grid.

  • Egypt to develop 700 MW of concentrated solar power by 2027

    The Egyptian Electricity Transmission Company (EETC) has signed an agreement with the International Finance Corporation (IFC) to develop a 600 MW solar power complex in Egypt’s West Nile province.Muneer Ferozie, IFC’s Regional Manager revealed the reports and said that the project will go in a long way to realizing the government’s renewable energy plan for 2035 to supply 20% of the generated e

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    Updating--Apr., 2019 Edition12 pages in total1. Overview (P2-3)2. Fact sheet (P4)3. Project Milestones (P5-6)4. Investment and Cost Breakdown (P8)5. Project Participants 5.1. Developer ‐‐‐ Noor Energy 1 (P9) 5.2. Owner & Investor ‐‐‐ Dubai Electricity and Water Authority (DEWA) (P9) 5.3. Owner & Investor ‐‐‐ ACWA Power (P9) 5.4. Owner & Investor ‐‐‐ Silk Road Fu

  • Morocco NOOR Ouarzazate 510MW CSP Project Report

    Updating--Feb., 2019 Edition20 pages in totalLocated in Ouarzazate Morocco, NOOR Ouarzazate (NOORo) is one of the biggest solar energy complex in the world. Consisting of four phases, NOORo project is part of Moroccan Renewable Energy Plan, which aims to 42% of RE installed capacity in national energy mix in 2020, and 52% in 2030 in Morocco. The NOORo I, II and III are CSP projects, with total cap

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • CSNP Royal Tech Urat 100MW Parabolic Trough CSP Project

    Updating--Feb., 2019 Edition8 pages in totalAs one of the first batch of 20 pilot CSPprojects, CSNP Royal Tech Urat 100MW Parabolic Trough CSP Project is thelargest trough plant within the pilot projects, in terms of installed capacity.1. Overview (P2)2. Fast sheet (P2-3)3. Highlights (P3)4. Project Milestones (P4)5. Project Participants 5.1. Developer--Inner Mongolia China Nuclear Royal Tech C

Upcoming Events

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news