Dubai 950MW NOOR Energy 1 CSP+PV Project

<BACK

   2020-2-26


Project Schedule


 ● January 9th, 2020CSP Tower completed

 ● November, 2019,1000 pylons intalled of CSP Tower project

 ● September 27th, 2019,30% construction work finished

 ● March, 2019,Financial Closed

 ● March 7th, 2019,Concrete base of Tower complete

 ● September, 2018,250MW PV added into the project

 ● December 21st, 2018,Approval for project construction

 ● July 18th, 2018,China President XI Jinping spoke high of the project in the UAE visiting

 ● April 13rd, 2018,EPC contract signed in Shanghai

 ● March 19th, 2018,Project Opening Ceremony

 ● December 13rd, 2017,Key EPC terms agreed

 ● September 16th, 2017,ACWA Power and Shanghai Electric win the bid

 ● June 5th, 2017,Bidding Open

 ● January 15th, 2017,Bidding announced

 ● 2016,RFP released

 ● May 29th, 2016,Project consultant selection


  Full report view online


Project Overview


Dubai 950MW NOOR Energy 1 CSP+PV Project is the largest CSP+PV solar project in the world, with total capacity of 950MW, including 3*200MW Parabolic Trough CSP plants, a 100MW Molten Salt Tower CSP Plant and PV power plant. The project is under the fourth phase of Mohammad Bin Rashid Al Maktoum Solar Park, which is designed to reach a total capacity of 5GW by 2030.


Basic Information

Location

Mohammed bin Rashid Solar Park,  Dubai, UAE

Installed Capacity

700MW CSP (3*200MW Parabolic Trough  + 100MW Tower)+ 250MW PV

Technology

Parabolic Trough + Molten Salt Tower  + PV

Storage

11.3h (Parabolic Trough CSP) / 15h  (Tower)

Starting Date

2018

Status

Under Construction

COD

700MW CSP to be completed by the end  of 2022

PPA/Tariff Period

35 Years

PPA/Tariff Rate

USD 7.3 cents/kWh

Reflector  Technology

Abengoa SpaceTube (8.2m)

Tower Technology  Provider

BrightSource Energy

Land Size

44 km2

Quantity of molten  salt

550,000 tons

Tower Height

260 m

                                           

Project Participants



 Plant photos



Latest News

See more+
  • New Confirmed Speakers - CSP Focus China 2020, Oct 22-23, Beijing China

    CSP Focus are pleased to announced new confirmed speakers from MASEN, Abengoa and Tsinghua University, on 10th Annual CSP Focus China 2020, which will convene on Oct 22 & 23 in Beijing China this year.Mr. Abderrahim Jamrani, Engineering Director, MASEN;Mr. Alberto Alba Rodríguez, Head of Business Development – Asia Pacific, Head of Battery Energy Storage Systems, Abengoa;Dr. Ning ZHANG,

  • Can NREL’s Fault-Finding Study Help Concentrated Solar Power?

    Concentrated solar power is facing its biggest opportunity in years with an important new tool at its disposal. As Spain considers procuring 5 gigawatts of CSP, the largest amount ever tendered, the sector is looking to avoid mistakes with a highly detailed best-practices guide.The Concentrating Solar Power Best Practices Study, published in June by the U.S. Department of Energy’s National Renewa

  • Abengoa advances in the construction of the world’s largest concentrated solar power complex in Dubai

    The company has just celebrated the completion of the first solar field of the three 200 MW parabolic trough plants which is building in phase IV of the Mohammed bin Rashid Al Maktoum (MBR) Solar Park, in the United Arab Emirates.Its construction has involved the installation and assembly of 2,120 collectors, each weighing 40 tons.Abengoa (MCE: ABG/P:SM), the international company that applies inn

  • Cerro Dominador Eyes on More CSP projects in Chile

    Chile has abundant solar resources. The Cerro Dominador project currently under construction is the first commercial CSP station in South America. The power station has an installed capacity of 110MW, with molten salt tower technology and a heat storage system, and can realize 24-hour uninterrupted power generation. The global economy is under the impact of the epidemic. What is the current constr

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news