Construction starts on China 1st pilot 50MW tower CSP project by SUPCON
2016.11.02 From: CSP Focus
Having successfully developed and operated China 1st commercial CSP project, SUPCON is well-known by China and global CSP industry as a pioneering tower CSP technology provider and project developer. SUPCON Delingha 10MW tower project was commissioned in the year of 2013, and its molten salt revamping project was completed earlier this year.
Freereport: SUPCON Delingha 10MW tower project report
Listed on the top of China 20 pilot projects launched by China government, Qinghai SUPCON Solar Delingha 50MW Molten Salt Tower CSP Project (6 hours storage) is to be leading the construction of China 1st phase 1.349GW pilot CSP projects. At the end of this October, the 50MW project was officially announced to break ground, just near to the site of its built 10MW plant.
The expected total investment is around RMB 1.05 billion, with the average of RMB 20,000/kW, which is the lowest among the other 19 pilot CSP projects. As Mr. Jin Jianxiang,Chairman of SUPCON Solar indicates, positively the investment could be controlled within RMB 1 billion thanks to SUPCON’s experience in both technology and construction, and the decreasing cost of components. Consideringthe DNI of China Delingha, the annual output is expected to be 1,360 millionkWh and operation 2720 hours. The project will enjoy the FiT of RMB 1.15/kWh, predicting a quite economic future of the project.
Freereport: List of China 1st Phase 20 CSP Pilot Projects
SUPCON says the capital fund (20% of total investment) has been raised by SUPCON itself, and the extra will be financed by the end of next year to ensure the procurement of equipment and construction.
More from CSP Focus
NextChina pilot CSP project--Supcon Solar Delingha 50MW CSP plant
Bidding update on SUPCON Delingha 50MW solar CSP tower project in China
SUPCON offer USD180m bidding price (USD105/㎡on solar field) for China 50MW CSP Tower hybrid project
SUPCON Solar Delingha 50MW molten salt tower CSP project recovers construction after winter stop
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower